Question 1
Original CAPM practice: 150 questions, 180 total answering minutes and 15 editorial pilot items. Complete and review Questions 1--75 before starting the 10-minute break. Starting the break permanently closes that section; you cannot return to its questions during or after the break. Then continue with Questions 76--150. The 180-minute budget is shared, with no fixed 90-minute section allowance. This booklet does not reproduce official software or predict an official score.
An incremental project will revisit next year's requirements after user feedback. Its next release still needs agreed acceptance criteria and a traceable record of approved decisions. How should the analyst organize the documentation?
- ☐ A. Approve the entire next-year specification first and apply its original detail to every subsequent release.
- ☐ B. Elaborate near-term requirements and maintain the decision record, then refine later requirements as evidence develops.
- ☐ C. Carry the original requirements baseline forward and record user feedback separately until the final project review.
- ☐ D. Document each delivered feature after acceptance, using the running software as the sole record during development.
Show answer and explanation
Response: B
Final answer: Elaborate near-term requirements and maintain the decision record, then refine later requirements as evidence develops.