CAPM Practice Test

150 questions · 180 total answering minutes; a 10-minute break after Question 75.

Original practice booklet. Record your answers, then open explanations after your attempt. Responses stay in this browser when storage is available. This booklet does not predict an official score.

Read the practice directions
This original study form contains 150 questions. Allow 180 total answering minutes. Complete and review Questions 1–75 before starting the 10-minute break. Starting the break permanently closes the first section; you cannot return to its questions during or after the break. Then continue with Questions 76–150 using the remaining answering time. The total time is shared; there is no prescribed 90-minute limit for either part. Choose one response for ordinary multiple-choice items. Where instructed, select exactly two responses. For matching items, record one target letter for each numbered prompt. For diagram-selection items, record the selected region label. Comic items use their illustrated exchange with a single-best-response question. Record responses before opening the explanations. This static practice adaptation does not reproduce official exam software, secure item allocation or an official passing score. Fifteen editorial pilot positions are documented for form planning, and every item provides an explanation. Check PMI's current testing instructions for your actual appointment. For calculations, practice with a basic onscreen calculator. PMI provides a built-in calculator for computer-based exams. At a test center, staff supply scratch materials and may provide a handheld calculator under the testing rules. PMI OnVUE testing uses a digital whiteboard; ordinary physical paper and writing materials are not permitted unless an approved accommodation applies. This booklet's response boxes are study workspaces and do not reproduce the official calculator or whiteboard. Follow the rules for your booked delivery mode.
Jump to a question

Question 1

Original CAPM practice: 150 questions, 180 total answering minutes and 15 editorial pilot items. Complete and review Questions 1--75 before starting the 10-minute break. Starting the break permanently closes that section; you cannot return to its questions during or after the break. Then continue with Questions 76--150. The 180-minute budget is shared, with no fixed 90-minute section allowance. This booklet does not reproduce official software or predict an official score.

An incremental project will revisit next year's requirements after user feedback. Its next release still needs agreed acceptance criteria and a traceable record of approved decisions. How should the analyst organize the documentation?

  • ☐ A. Approve the entire next-year specification first and apply its original detail to every subsequent release.
  • ☐ B. Elaborate near-term requirements and maintain the decision record, then refine later requirements as evidence develops.
  • ☐ C. Carry the original requirements baseline forward and record user feedback separately until the final project review.
  • ☐ D. Document each delivered feature after acceptance, using the running software as the sole record during development.
Show answer and explanation

Response: B

Final answer: Elaborate near-term requirements and maintain the decision record, then refine later requirements as evidence develops.

The next release needs requirements that developers can implement and testers can assess. Keep the traceable decision record. User feedback supports subsequent refinement of the requirements planned for next year's releases.

Question 2

At a reporting date, a project has planned value of $48,000, earned value of $42,000 and actual cost of $45,000. What is its cost variance?

  • ☐ A. -$3,000
  • ☐ B. +$6,000
  • ☐ C. -$6,000
  • ☐ D. +$3,000
Show answer and explanation

Response: A

Final answer: -$3,000

Subtract the $45,000 actual cost from the $42,000 earned value to obtain a cost variance of -$3,000, indicating an unfavorable cost result for the completed work.

Question 3

Use the roadmap and its dependency labels. Select the release card containing the direct prerequisite for shipment tracking.

A. Release 1: Account setupB. Release 2: Order placementC. Release 3: Shipment trackingD. Release 4: ReturnsDependencies: A to B; B to C

Scroll the diagram sideways on a narrow screen.

Diagram text description

Card A: release 1, Account setup. Card B: release 2, Order placement. Card C: release 3, Shipment tracking. Card D: release 4, Returns. Dependencies: A before B; B before C.

Record the label of the selected region.

Show answer and explanation

Response: B

Final answer: Card B

Choose card B, Release 2. The drawn chain connects order placement directly to shipment tracking, making Release 2 the immediate prerequisite requested.

Question 4

An adaptive software team must retain legally required validation records. A member argues that preferring working software means the records should be omitted. What is the best interpretation?

  • ☐ A. Omit the records whenever a working feature is available.
  • ☐ B. Keep the required records while using working software and feedback to guide delivery.
  • ☐ C. Stop incremental delivery until every possible document has been completed.
  • ☐ D. Let each developer decide which legal records are worth keeping.
Show answer and explanation

Response: B

Final answer: Keep the required records while using working software and feedback to guide delivery.

The team must retain the validation records required by law as it develops working software and uses feedback to decide what to deliver next. The adaptive preference guides how development proceeds within those obligations.

Question 5

A system is technically complete, but the support team has not received operating instructions or practiced its recovery procedure. Operations takes responsibility next week. What should the project team address before transition?

  • ☐ A. Extend the project team's technical test cycle and treat its passing results as evidence of support readiness.
  • ☐ B. Transfer responsibility on the agreed date and add the missing instructions to the next operational improvement backlog.
  • ☐ C. Obtain final acceptance from the sponsor and schedule the support team's recovery practice after operations takes responsibility.
  • ☐ D. Arrange the operating instructions and recovery practice with the receiving support team before handover.
Show answer and explanation

Response: D

Final answer: Arrange the operating instructions and recovery practice with the receiving support team before handover.

Prepare the receiving support team. Arrange the missing operating instructions and recovery practice before next week's handover so the people taking responsibility can use the system and respond to a recovery need.

Question 6

A facility project has agreed specifications, established construction methods and a required sequence of inspections. Stakeholders expect little scope change and need an early integrated cost and schedule plan. Which approach is best supported by these characteristics?

  • ☐ A. An incremental approach that approves cost and sequencing separately for each newly selected facility component.
  • ☐ B. A predictive approach with early planning and controlled review of changes.
  • ☐ C. A hybrid approach that defers design choices to trade-level iterations while fixing only inspection milestones.
  • ☐ D. An adaptive approach that establishes facility scope through successive construction increments and feedback.
Show answer and explanation

Response: B

Final answer: A predictive approach with early planning and controlled review of changes.

The facility's agreed specifications let the team establish a plan before construction, incorporating the known inspection sequence into the schedule and estimating costs from established methods. Scope is expected to stay stable. A predictive approach therefore supports the early integrated plan the stakeholders need, with later changes examined through the applicable review process.

Question 7

Several Agile Teams contribute to one large product and need a shared business mission, coordinated planning and integrated demonstrations. Which SAFe construct directly organizes this team-of-teams delivery?

  • ☐ A. A team-level Iteration Planning event used to agree on near-term work.
  • ☐ B. An Agile Release Train.
  • ☐ C. A Scrum of Scrums meeting used to raise cross-team impediments.
  • ☐ D. A Lean Portfolio Management function used to align investment with strategy.
Show answer and explanation

Response: B

Final answer: An Agile Release Train.

Several delivery teams are coordinating a shared business mission through common planning and integrated demonstrations. This is an Agile Release Train. SAFe describes that organization at the team-of-teams level, with train-level events coordinating delivery across the participating teams.

Question 8

Which description best represents the purpose of a user story?

  • ☐ A. A structured sequence of actor-system interactions that records a success path and its alternate flows.
  • ☐ B. A concise description of desired functionality from a user perspective, developed through discussion and confirmation.
  • ☐ C. A detailed interface specification that defines field formats and message handling for implementation.
  • ☐ D. A release acceptance checklist that records the evidence used to approve the completed product.
Show answer and explanation

Response: B

Final answer: A concise description of desired functionality from a user perspective, developed through discussion and confirmation.

A user story gives a concise account of functionality from the user's perspective, providing a starting point for discussion and confirmation as the team develops detail for delivery.

Question 9

During refinement, Developers find that a high-priority Product Backlog item is too large to complete within one Sprint. The Product Owner still wants its value delivered soon. What should the team do?

  • ☐ A. Select it unchanged and extend the Sprint until it is finished.
  • ☐ B. Treat each technical phase as a finished Increment even if no usable result exists.
  • ☐ C. Break down and clarify the item into smaller pieces suitable for selection and completion within a Sprint.
  • ☐ D. Remove the item solely because it cannot fit in its current form.
Show answer and explanation

Response: C

Final answer: Break down and clarify the item into smaller pieces suitable for selection and completion within a Sprint.

Refine the oversized backlog item. Developers and the Product Owner can split and clarify its work into useful pieces that can each be selected and completed within a Sprint.

Question 10

Developers need precise interface behavior, while customer service leaders need to understand how the proposed behavior changes claim handling. What should the analyst do?

  • ☐ A. Use audience-appropriate explanations and models while preserving the same agreed requirement.
  • ☐ B. Prepare a business summary that omits disputed interface behavior so the service leaders can approve sooner.
  • ☐ C. Present the interface model to both groups and ask customer service to use its technical terms for approval.
  • ☐ D. Seek separate sign-offs on independently revised descriptions, then reconcile any differences during implementation.
Show answer and explanation

Response: A

Final answer: Use audience-appropriate explanations and models while preserving the same agreed requirement.

Customer service handles the claims. Explain what the revised behavior means in that work, and give Developers the precise interface description they need to implement the same agreed requirement. Check the representations for consistency.

Question 11

A project manager in a matrix organization needs two engineers for planned design work. Their functional manager also assigns their departmental work. Both managers have defined authority over resource assignments. What should the project manager do?

  • ☐ A. Ask the sponsor to assign both engineers to the project before discussing their departmental commitments.
  • ☐ B. Coordinate with the functional manager to agree on availability and assignments for the planned work.
  • ☐ C. Ask the engineers to choose which manager's work to perform and update the project forecast from their choices.
  • ☐ D. Reserve the engineers against the approved schedule and send the functional manager the allocation afterward.
Show answer and explanation

Response: B

Final answer: Coordinate with the functional manager to agree on availability and assignments for the planned work.

Both managers share resource authority over the engineers. They need to agree on availability that accounts for departmental commitments and the planned design work before assignments are made. Coordination with the functional manager provides that agreement, with the applicable escalation route available if an impasse remains unresolved.

Question 12

A test passed for the original rule allowing a maximum of ten records. The approved requirement now permits twenty records. What should the analyst recognize about the existing result?

  • ☐ A. It does not by itself verify the new twenty-record behavior.
  • ☐ B. Mark the requirement verified using the approval record and attach the earlier test as supporting documentation.
  • ☐ C. Reclassify the earlier result as failed because changing the limit invalidates its original ten-record finding.
  • ☐ D. Retain the passed result as full verification because the approved change alters a limit rather than the underlying function.
Show answer and explanation

Response: A

Final answer: It does not by itself verify the new twenty-record behavior.

The changed requirement allows twenty records. Test that approved limit and its boundary to establish whether the revised behavior works. Keep the earlier passing result as evidence of what happened in the ten-record test.

Question 13

A plan assumes the same specialist will perform two full-time activities during the same week. Each activity needs that specialist throughout, and there is no substitute. Which planning problem should be resolved?

  • ☐ A. A resource-cost assumption that can be corrected by charging one assignment to a different cost account.
  • ☐ B. A duration estimate that can be shortened for both activities while retaining the same specialist and workload.
  • ☐ C. A schedule dependency that can be resolved by changing the links while keeping both full-time assignments in the same week.
  • ☐ D. An infeasible resource allocation that affects the schedule.
Show answer and explanation

Response: D

Final answer: An infeasible resource allocation that affects the schedule.

The specialist is allocated twice. Two simultaneous full-time activities each need the same person throughout, so the schedule demands capacity that the team does not have and must be reconciled with available resources.

Question 14

A similar completed project recorded that an approval handoff was missed until user testing. How should the analyst use that lesson in the new requirements effort?

  • ☐ A. Adopt the previous project's handoff requirement and seek confirmation only when the new product reaches testing.
  • ☐ B. Add the omitted handoff to the current scope baseline before checking whether the departments have the same responsibilities.
  • ☐ C. Record the lesson as a delivery risk and defer the handoff discussion until the implementation team is selected.
  • ☐ D. Check whether a comparable handoff applies and include the relevant stakeholders and requirements if it does.
Show answer and explanation

Response: D

Final answer: Check whether a comparable handoff applies and include the relevant stakeholders and requirements if it does.

The earlier approval problem gives the analyst a possible dependency to investigate. Ask the current stakeholders about the handoff. Their account will establish whether it applies here and what responsibilities or requirements need attention before work is committed.

Question 15

A Product Owner asks a business analyst to write and clarify some Product Backlog items. The analyst does that work. Who remains accountable for effective Product Backlog management in Scrum?

  • ☐ A. The business analyst, because writing the items transfers the accountability.
  • ☐ B. The Developers collectively, because they estimate and implement the selected items.
  • ☐ C. The Product Owner
  • ☐ D. The Scrum Master, because the Scrum Master is accountable for all backlog content.
Show answer and explanation

Response: C

Final answer: The Product Owner

The Product Owner remains accountable for effective Product Backlog management when delegating preparation and clarification to an analyst.

Question 16

All four requirements in the traceability graphic need passing test evidence before release. Select the row that prevents readiness from being established.

A. R1: implementation Complete; test PassedB. R2: implementation Complete; test Not runC. R3: implementation Complete; test PassedD. R4: implementation Complete; test Passed

Scroll the diagram sideways on a narrow screen.

Diagram text description

Row A: R1; implementation Complete; test Passed. Row B: R2; implementation Complete; test Not run. Row C: R3; implementation Complete; test Passed. Row D: R4; implementation Complete; test Passed.

Record the label of the selected region.

Show answer and explanation

Response: B

Final answer: Row B

R2 is in row B. The release condition requires every requirement to have a passing test result, and this completed implementation is still waiting for its required test to run.

Question 17

A project has earned $36,000 of budgeted work value by a date when $40,000 was planned. Actual cost is $34,000. Which statement correctly interprets schedule variance?

  • ☐ A. Schedule variance is +$2,000, meaning the project finishes two days early.
  • ☐ B. Schedule variance is -$6,000, calculated by subtracting planned value from actual cost.
  • ☐ C. Schedule variance is -$4,000, showing a $4,000 shortfall in completed budgeted work at the reporting date.
  • ☐ D. Schedule variance is +$4,000, meaning more work has been completed than planned.
Show answer and explanation

Response: C

Final answer: Schedule variance is -$4,000, showing a $4,000 shortfall in completed budgeted work at the reporting date.

Subtracting the $40,000 planned value from the $36,000 earned value produces a schedule variance of -$4,000, representing the shortfall in completed budgeted work at the reporting date and requiring schedule-network evidence to translate its implications into a completion-date estimate.

Question 18

Match each Scrum artifact with its commitment. Artifacts: 1. Product Backlog; 2. Sprint Backlog; 3. Increment. Commitments: A. Definition of Done; B. Product Goal; C. Sprint Goal. Use each commitment once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--B; 2--C; 3--A

Final answer: 1--B; 2--C; 3--A

The Product Backlog's commitment is the Product Goal. Match it to B. The Sprint Goal focuses the Sprint Backlog on its current objective, and the Definition of Done establishes the required quality state of the Increment, completing 2-C and 3-A.

Question 19

Requirements for next month are well understood, while a possible capability for next year still needs research. How should the roadmap reflect that difference?

  • ☐ A. Show greater detail for nearer work and less detail for the uncertain later capability.
  • ☐ B. Give both horizons the same detailed feature commitments so stakeholders can compare releases on equal terms.
  • ☐ C. Remove the tentative capability from the roadmap and keep it only in the research team's working notes.
  • ☐ D. Show the later capability as a committed feature with a precise date, recording its uncertainty in the risk register.
Show answer and explanation

Response: A

Final answer: Show greater detail for nearer work and less detail for the uncertain later capability.

The analyst has enough information to detail next month's work. Research is still needed for the next-year capability, so the roadmap can retain it as tentative direction for later refinement.

Question 20

During a meeting to approve an installation sequence, a participant raises a useful idea about next year's staff training. The idea does not affect today's decision. What should the facilitator do?

  • ☐ A. Capture it for appropriate later follow-up and return to the installation objective.
  • ☐ B. Ask for an immediate vote on the training idea to close that topic before discussing the installation sequence.
  • ☐ C. Add training design to the meeting's approval criteria so both decisions can be resolved with the same attendees.
  • ☐ D. Ask the participant to develop the training proposal during the meeting, then return to the installation decision.
Show answer and explanation

Response: A

Final answer: Capture it for appropriate later follow-up and return to the installation objective.

Keep the installation decision on track. Recording the training idea preserves it for an appropriate later discussion because next year's training does not affect the installation sequence being approved today.

Question 21

Three departments have interdependent requirements and disagree about the handoff between them. Their representatives can meet together. Which method best supports joint resolution?

  • ☐ A. A facilitated requirements workshop involving the relevant departments.
  • ☐ B. Prototype one department's preferred interface and use a demonstration to obtain the others' approval.
  • ☐ C. Interview each department separately and choose the handoff supported by the greatest number of representatives.
  • ☐ D. Circulate a draft interface requirement for written sign-off and leave conflicting comments for implementation review.
Show answer and explanation

Response: A

Final answer: A facilitated requirements workshop involving the relevant departments.

The handoff crosses departmental work boundaries, so representatives need to examine shared examples together and resolve the interdependent requirements in a facilitated workshop. Separate interviews can prepare that discussion.

Question 22

A communications plan assigns a weekly cost forecast to the finance lead through the approved reporting portal. The associate has prepared the forecast. Which action applies that plan?

  • ☐ A. Upload the forecast on time and notify the sponsor instead of routing it to the finance lead for review.
  • ☐ B. Email the finance lead when the forecast is ready and upload it to the portal at the next milestone review.
  • ☐ C. Submit the forecast through the portal to the finance lead at the planned reporting time.
  • ☐ D. Wait for the project manager's next status meeting and include the forecast with that meeting's materials.
Show answer and explanation

Response: C

Final answer: Submit the forecast through the portal to the finance lead at the planned reporting time.

Submit the completed forecast to the finance lead through the approved portal at the weekly time established in the communications plan.

Question 23

An analyst needs to describe how a user and system interact to complete a refund, including the normal flow and exception when payment fails. Which representation is most suitable?

  • ☐ A. A requirements traceability matrix linking the refund requirement to a design element and test identifier.
  • ☐ B. A use case with the success flow and relevant alternate or exceptional paths.
  • ☐ C. A user story stating the user's refund goal without elaborating its interaction or exception behavior.
  • ☐ D. A data dictionary defining the refund fields and their formats without describing the interaction sequence.
Show answer and explanation

Response: B

Final answer: A use case with the success flow and relevant alternate or exceptional paths.

A use case describes the actor-system interaction toward the refund goal, giving the analyst a way to record its successful path and payment-failure exception before the team implements that behavior.

Question 24

A company wants a Scrum Team to deliver a usable ordering feature. Its proposed team contains only analysts; every implementation and testing request would wait in separate departmental queues. Which change best supports the proposed team responsibility?

  • ☐ A. Measure the analysts by the number of requests sent to other departments.
  • ☐ B. Keep the analyst-only team and use more detailed requests to the other queues.
  • ☐ C. Provide a cross-functional team with the capabilities needed to produce a usable Increment.
  • ☐ D. Assign a manager to approve each handoff without changing access to skills.
Show answer and explanation

Response: C

Final answer: Provide a cross-functional team with the capabilities needed to produce a usable Increment.

Implementation and testing are stuck in departmental queues. Add the delivery capabilities the team lacks. A cross-functional Scrum Team needs the skills required to create a usable ordering Increment within the Sprint, including implementing and testing the feature.

Question 25

Read the comic. What conclusion about acceptance is supported by the reported result?

Panel 1. Tessa: Export files must include all four mandatory fields.Panel 2. Malik: The export runs successfully.Panel 3. Tessa: The fourth field is missing from the results.

Scroll the diagram sideways on a narrow screen.

Diagram text description

Panel 1. Tessa: Export files must include all four mandatory fields. Panel 2. Malik: The export runs successfully. Panel 3. Tessa: The fourth field is missing from the results.

  • ☐ A. Successful execution does not establish acceptance because a required field is missing.
  • ☐ B. Treat the execution test as sufficient acceptance evidence and record the missing field as a subsequent enhancement.
  • ☐ C. Revise the acceptance criterion to the three generated fields and retain the existing result as a passing test.
  • ☐ D. Accept the export function provisionally because its processing succeeded, without retesting the mandatory content.
Show answer and explanation

Response: A

Final answer: Successful execution does not establish acceptance because a required field is missing.

Acceptance requires all four mandatory fields in the export. One is missing, so the successful execution has not yet supplied evidence that the agreed content criterion is met. Addressing the gap and obtaining the applicable acceptance evidence are necessary under that criterion. A change to it needs authorization.

Question 26

A simple unconstrained project has two independent start-to-finish paths, each 15 days long. No shorter path exists. Management shortens one path to 13 days and leaves the other unchanged. What is the resulting project duration?

  • ☐ A. 13 days
  • ☐ B. 28 days
  • ☐ C. 15 days
  • ☐ D. 14 days
Show answer and explanation

Response: C

Final answer: 15 days

The unchanged path still needs fifteen days to reach Finish. Both paths must finish. It therefore controls completion after the revised thirteen-day path is done, giving the project a fifteen-day duration under the stated network assumptions.

Question 27

Which two practices support analysis in an adaptive project? Select two.

  • ☐ A. Carry the original release requirements forward unchanged until the final project acceptance review.
  • ☐ B. Complete and baseline all future requirement detail before collecting feedback from the first release.
  • ☐ C. Defer acceptance criteria until the implemented feature is demonstrated to its users.
  • ☐ D. Use relevant feedback from delivered increments to review future requirements.
  • ☐ E. Refine upcoming work as it approaches implementation.
Show answer and explanation

Response: D, E

Final answer: Refine upcoming work as it approaches implementation.; Use relevant feedback from delivered increments to review future requirements.

Upcoming work needs refinement. Feedback from delivered increments supplies evidence about future requirements, and elaborating that work as implementation approaches lets the analyst use the latest understanding when developing its detail.

Question 28

An organization configures and launches a new returns portal by December. After launch, a service team processes customer returns through it every day. Which statement correctly distinguishes the work?

  • ☐ A. The recurring processing becomes a project whenever the service team applies a new procedure.
  • ☐ B. The launch and recurring processing are both operations because the same organization staffs the work.
  • ☐ C. The launch and recurring processing are both projects because each creates a completed customer outcome.
  • ☐ D. The portal launch is a project, and the recurring returns processing is operations.
Show answer and explanation

Response: D

Final answer: The portal launch is a project, and the recurring returns processing is operations.

Identify the portal-launch initiative first. Its December endpoint and creation of a new capability establish a project, with the service team subsequently taking responsibility for recurring customer-return processing as ongoing operations.

Question 29

A project uses predictive planning for a regulated installation and adaptive development for an uncertain user interface. What should the analyst do?

  • ☐ A. Baseline all installation and interface requirements together before permitting either part to begin delivery.
  • ☐ B. Refine the interface independently and reconcile its installation constraints during the final integration review.
  • ☐ C. Tailor the requirements work and coordination to each part while maintaining consistency across their dependency.
  • ☐ D. Use the installation change-control cycle for every interface detail so both parts follow the same analysis cadence.
Show answer and explanation

Response: C

Final answer: Tailor the requirements work and coordination to each part while maintaining consistency across their dependency.

The installation has stable regulatory requirements. The analyst can use controlled planning there and refine the uncertain interface requirements through user feedback, coordinating changes across their shared dependency so the two deliveries remain compatible.

Question 30

A team's explicit Kanban policy allows at most three items in its testing state. Three items are already there, one of which is blocked. A fourth development item is ready for testing. The policy specifies no exception. What action best follows the team's WIP control?

  • ☐ A. Move the fourth item into testing because completed development takes priority over the state limit.
  • ☐ B. Reset the limit to four for this item without discussing or updating the explicit workflow policy.
  • ☐ C. Move the fourth item into testing and exclude the blocked item from the WIP count.
  • ☐ D. Help resolve or complete current testing work before pulling the fourth item into that state.
Show answer and explanation

Response: D

Final answer: Help resolve or complete current testing work before pulling the fourth item into that state.

The blocked Testing card has started and remains unfinished, making it part of WIP under the explicit policy. Testing already holds three items. Pulling a fourth would breach that limit.

Question 31

An associate needs the current assessed risk events and their owners, together with the agreed process for assessing and reviewing those risks. Which two records directly provide that information? Select two.

  • ☐ A. The current risk register with assessed events and assigned owners.
  • ☐ B. The stakeholder register describing affected people and their engagement needs.
  • ☐ C. The agreed risk management plan describing the response and review process.
  • ☐ D. The issue log describing problems that have already occurred.
  • ☐ E. The change log describing requests submitted for approval.
Show answer and explanation

Response: A, C

Final answer: The current risk register with assessed events and assigned owners.; The agreed risk management plan describing the response and review process.

The register identifies the assessed risk events and the people responsible for them. To decide how to manage that recorded exposure, the associate also needs the risk management plan, which sets out the team's agreed approach to its risk work.

Question 32

In this workflow, work starts when a card enters In progress and finishes when it enters Done. Select the labeled card counted as work in progress under these boundaries.

RequestedIn progressTestingDoneA. Request reviewB. New requestC. Blocked testD. Released fix

Scroll the diagram sideways on a narrow screen.

Diagram text description

Columns: Requested, In progress, Testing, Done. Cards: A: Request review, in Requested. B: New request, in Requested. C: Blocked test, in Testing. D: Released fix, in Done.

Record the label of the selected region.

Show answer and explanation

Response: C

Final answer: Card C

Card C has started and remains unfinished in Testing, satisfying the stated work-in-progress boundaries. Select C. Follow the card's current position from In progress toward its required Done endpoint.

Question 33

The customer has accepted the deliverables. A team member proposes immediately deleting project records and releasing everyone before outstanding contractual closure work is checked. Which action is appropriate?

  • ☐ A. Archive the accepted deliverables now and treat the acceptance record as confirmation that all project obligations are closed.
  • ☐ B. Complete the applicable closure activities, including contractual checks, records and resource transition.
  • ☐ C. Release all project resources after customer acceptance and let procurement complete the remaining contractual checks independently.
  • ☐ D. Retain the team until the next operational review, postponing closure documentation until product performance is measured.
Show answer and explanation

Response: B

Final answer: Complete the applicable closure activities, including contractual checks, records and resource transition.

Contractual closure work remains outstanding. The team needs to check those obligations and complete the administrative arrangements, preserving the project records and coordinating the resource transition as part of finishing the project.

Question 34

Activity K cannot start until both predecessors finish. Their early finish times are elapsed day 9 and elapsed day 14. The relationships are finish-to-start with zero lag. What is K's early start?

  • ☐ A. Elapsed day 14
  • ☐ B. Elapsed day 23
  • ☐ C. Elapsed day 9
  • ☐ D. Elapsed day 11.5
Show answer and explanation

Response: A

Final answer: Elapsed day 14

K starts at elapsed day 14. Its two incoming dependencies require both predecessors to finish, so the later finish at day 14 establishes when K can begin in this unconstrained network.

Question 35

Match each action to its primary emphasis: 1. Build a shared direction and motivate the team; 2. Establish assignments and compare delivery with the plan. Emphases: A. Management; B. Leadership. Use each once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--B; 2--A

Final answer: 1--B; 2--A

Match 1 to B. Building a shared direction motivates the team through leadership, and the assignment and delivery-monitoring duties in action 2 complete the management role needed for 2-A.

Question 36

Two groups provide requirements for a shared process, but nobody knows who can approve a conflict between them. What should the analyst clarify?

  • ☐ A. The technical preference of the development team that will implement the shared process.
  • ☐ B. The relevant stakeholder roles and decision responsibilities.
  • ☐ C. The group with the largest number of users, so its representative can approve any conflicting requirement.
  • ☐ D. The sequence in which the two groups submitted their requirements and the dates their drafts were recorded.
Show answer and explanation

Response: B

Final answer: The relevant stakeholder roles and decision responsibilities.

Requirement providers disagree. Establish their relevant roles and authorized responsibilities so the analyst can identify the approval route for resolving that disagreement before treating a requirement as agreed.

Question 37

Read the planning cards. Select the card that represents a milestone.

A. Launch Approved: 0 daysB. Installation: 3 daysC. Training: 5 daysD. Documentation: 2 days

Scroll the diagram sideways on a narrow screen.

Diagram text description

Card A: Launch Approved, 0 days. Card B: Installation, 3 days. Card C: Training, 5 days. Card D: Documentation, 2 days.

Record the label of the selected region.

Show answer and explanation

Response: A

Final answer: Card A

Choose A, Launch Approved. Its zero-duration marker identifies the significant event represented by a milestone.

Question 38

Read the comic. What should Ana do next?

Panel 1. Ana: The requirement says send the confirmation promptly.Panel 2. Ellis: I interpreted that as within a day.Panel 3. Noor: Customers need it within five minutes.

Scroll the diagram sideways on a narrow screen.

Diagram text description

Panel 1. Ana: The requirement says send the confirmation promptly. Panel 2. Ellis: I interpreted that as within a day. Panel 3. Noor: Customers need it within five minutes.

  • ☐ A. Record both interpretations as alternatives and let the development team select one during implementation.
  • ☐ B. Adopt the service lead's five-minute target as an approved requirement without confirming its intended conditions.
  • ☐ C. Clarify and agree on a measurable timing requirement with the relevant stakeholders.
  • ☐ D. Adopt the developer's one-day interpretation because it is the only estimate supplied by the implementation team.
Show answer and explanation

Response: C

Final answer: Clarify and agree on a measurable timing requirement with the relevant stakeholders.

The timing requirement needs a measurable limit and agreed conditions. Ana can bring the developer's implementation knowledge and the service lead's account of customer needs into a discussion with the relevant stakeholders. Their agreement establishes what 'promptly' means for this service and provides the requirement to document.

Question 39

The approved role assignments make the technical lead responsible for accepting engineering results, the sponsor responsible for budget decisions, and procurement responsible for negotiating vendor contracts. The project manager coordinates delivery. A vendor asks the project manager to confirm technical acceptance of a prototype. Which response follows these assignments?

  • ☐ A. Confirm technical acceptance personally because the project manager coordinates delivery.
  • ☐ B. Send the prototype to the sponsor and ask for a budget approval as the acceptance decision.
  • ☐ C. Ask procurement to treat completion of the contract negotiation as technical acceptance.
  • ☐ D. Give the prototype evidence to the technical lead and coordinate obtaining the acceptance decision.
Show answer and explanation

Response: D

Final answer: Give the prototype evidence to the technical lead and coordinate obtaining the acceptance decision.

Send the evidence to the technical lead, whose assigned role includes accepting engineering results. The project manager can coordinate that review.

Question 40

A predictive project needs sufficiently developed requirements to support an early integrated scope and delivery plan. How should the analyst contribute?

  • ☐ A. Develop the detailed requirements one release at a time after committing to the complete installation budget.
  • ☐ B. Gather early stakeholder requirements but allow later clarifications to enter scope without the agreed impact review.
  • ☐ C. Use the first requirements draft as the scope baseline and resolve any remaining ambiguity during installation.
  • ☐ D. Elicit and analyze the needed requirements early, then manage applicable changes through the agreed controls.
Show answer and explanation

Response: D

Final answer: Elicit and analyze the needed requirements early, then manage applicable changes through the agreed controls.

Integrated predictive planning needs sufficiently clear scope and delivery information. The analyst obtains that basis by eliciting and analyzing requirements early enough for the plan to use them.

Question 41

A team knows the business goal but expects user feedback to change which features best achieve it. Small usable releases can be evaluated safely. Which two characteristics support an adaptive approach? Select two.

  • ☐ A. The product can be evaluated only after a single completed delivery and its requirements are fixed.
  • ☐ B. Delivery must follow a prescribed sequence whose detailed design is settled before work begins.
  • ☐ C. The required solution and detailed requirements are stable and already agreed by the key users.
  • ☐ D. Usable increments can provide evidence for later choices.
  • ☐ E. Requirements are expected to evolve through feedback.
Show answer and explanation

Response: D, E

Final answer: Requirements are expected to evolve through feedback.; Usable increments can provide evidence for later choices.

The business goal is known. Small usable releases let users evaluate which features achieve it, and the feedback from those evaluations can guide evolving requirements for the team's subsequent work.

Question 42

Capability B requires capability A to be usable. Neither exists yet. The roadmap has room for only one of them in the next release. Which sequence respects that dependency?

  • ☐ A. Deliver A before B, subject to the relevant value and readiness decisions.
  • ☐ B. Split the release effort equally between A and B so both appear on the release forecast without either being usable.
  • ☐ C. Select whichever capability has the larger stated benefit and defer the prerequisite decision until release testing.
  • ☐ D. Deliver B first and schedule its acceptance after A, even though the release must contain a usable capability.
Show answer and explanation

Response: A

Final answer: Deliver A before B, subject to the relevant value and readiness decisions.

B cannot be usable until A is usable. Deliver A first. That establishes the dependency needed for a later release of B, subject to the relevant value and readiness decisions.

Question 43

Read the comic. Which action follows the agreed risk response?

Panel 1. Mei: Our plan calls for the alternate supplier if stock isnot confirmed by noon.Panel 2. Jules: It is 12:30. The supplier confirmed there is no stock.Panel 3. Mei: The risk owner is available now.

Scroll the diagram sideways on a narrow screen.

Diagram text description

Panel 1. Mei: Our plan calls for the alternate supplier if stock is not confirmed by noon. Panel 2. Jules: It is 12:30. The supplier confirmed there is no stock. Panel 3. Mei: The risk owner is available now.

  • ☐ A. Inform the risk owner of the confirmed trigger and begin the authorized alternate-supplier response.
  • ☐ B. Request fresh approval of the alternate-supplier strategy and hold the response despite the existing authorization.
  • ☐ C. Ask the first supplier to confirm a revised deadline before notifying the risk owner or activating the alternate source.
  • ☐ D. Document the shortage as an issue and defer the response decision until the next scheduled risk review.
Show answer and explanation

Response: A

Final answer: Inform the risk owner of the confirmed trigger and begin the authorized alternate-supplier response.

The supplier has reported no stock at 12:30, after the noon confirmation deadline that triggers the planned response. Notify the available risk owner and begin the authorized alternate-supplier action.

Question 44

An authorized stakeholder requests a new feature after the predictive scope baseline is approved. The request may affect cost and installation dates, and the change-control procedure requires impact review before approval. What should the associate do next?

  • ☐ A. Obtain the stakeholder's written confirmation and add the feature before estimating its installation impact.
  • ☐ B. Estimate the cost effect and ask the delivery team to absorb any schedule change within the current baseline.
  • ☐ C. Ask the sponsor to approve the feature in principle and revise the baseline before completing the impact review.
  • ☐ D. Record the change request and support the required impact review through the agreed procedure.
Show answer and explanation

Response: D

Final answer: Record the change request and support the required impact review through the agreed procedure.

The stakeholder has requested a change. Record it and assess the possible cost and installation effects through the agreed change-control procedure. The request then needs the separate approval decision assigned by that procedure.

Question 45

A project manager asks an associate to lead a specialist testing activity. The associate understands the product but has never used the required testing method. A qualified specialist can supervise, and the manager is willing to adjust the assignment. Which response best supports a responsible decision?

  • ☐ A. Accept the full assignment and arrange informal coaching without telling the manager about the gap.
  • ☐ B. Accept because product knowledge is sufficient to replace experience with the specified testing method.
  • ☐ C. Explain the qualification gap and agree on qualified supervision and an appropriate scope before accepting.
  • ☐ D. Refuse any participation because an unfamiliar method prevents the associate from taking a developmental role.
Show answer and explanation

Response: C

Final answer: Explain the qualification gap and agree on qualified supervision and an appropriate scope before accepting.

The associate lacks experience with the proposed method. Explain that gap to the manager before accepting the assignment, allowing a suitable scope and specialist supervision to support learning on the work.

Question 46

A report shows SPI = 1.08. The current network schedule also shows a critical-path activity delayed by four days with no available float, and no recovery action is planned. What should the associate report?

  • ☐ A. Use the positive SPI to offset the four-day critical-path delay in the completion forecast without a recovery plan.
  • ☐ B. Treat SPI and the network delay as inconsistent results and withhold both until the next earned-value report.
  • ☐ C. Report an ahead-of-schedule finish because SPI exceeds one, recording the delayed activity only as a local task issue.
  • ☐ D. Report SPI = 1.08 alongside the four-day critical-path delay that threatens the completion date.
Show answer and explanation

Response: D

Final answer: Report SPI = 1.08 alongside the four-day critical-path delay that threatens the completion date.

An SPI of 1.08 means 1.08 units of earned value for each unit of planned value at the reporting date. Check the controlling activity too. Its four-day delay has no float or recovery, leaving the finish date threatened, so stakeholders need that network information alongside the SPI.

Question 47

A coordinator needs to check which individuals are affected by a migration and the roles they hold. Which record most directly provides that identification information?

  • ☐ A. The stakeholder register
  • ☐ B. The issue log
  • ☐ C. The risk register
  • ☐ D. The cost baseline
Show answer and explanation

Response: A

Final answer: The stakeholder register

The stakeholder register records affected people or groups and their roles. Those entries give the coordinator the identification information needed when considering who should participate in the migration.

Question 48

The diagram shows four zero-lag finish-to-start branches between the same Start and Finish milestones. Resources are unconstrained, and no external dates apply. Select the labeled branch that controls the earliest Finish.

StartFinishA: K 4 days then L 3 daysB: M 5 days then N 4 daysC: P 2 days then Q 4 daysD: R 3 days then S 2 days

Scroll the diagram sideways on a narrow screen.

Diagram text description

Start connects to each parallel branch; every branch connects to Finish. A: K lasting 4 days then L lasting 3 days. B: M lasting 5 days then N lasting 4 days. C: P lasting 2 days then Q lasting 4 days. D: R lasting 3 days then S lasting 2 days.

Record the label of the selected region.

Show answer and explanation

Response: B

Final answer: Branch B

The Finish milestone waits for every incoming branch, so add the durations along each branch to determine when its work arrives. Branch B needs nine days. The other branches reach Finish within seven days, leaving B's five-day and four-day activities to set the earliest completion of the network.

Question 49

A product team needs to communicate the direction of its service and the sequence of intended capabilities across upcoming releases. Which artifact best serves that purpose?

  • ☐ A. A project charter authorizing the initiative and identifying its high-level purpose.
  • ☐ B. A release test plan specifying how the next delivered product will be verified.
  • ☐ C. A product roadmap
  • ☐ D. A Product Backlog ordering the individual items available for future team work.
Show answer and explanation

Response: C

Final answer: A product roadmap

A product roadmap shows the intended service direction and sequence of capabilities across upcoming releases, giving the team the planning view requested in this case.

Question 50

The schedule assumes a supplier will provide a test device on Monday. The supplier has not confirmed the date, and delay would affect testing. What should the associate do?

  • ☐ A. Retain Monday as a confirmed schedule input because the supplier has not proposed a different date.
  • ☐ B. Add schedule contingency without seeking confirmation or recording the assumption behind the testing date.
  • ☐ C. Record and validate the assumption, considering the related delivery risk.
  • ☐ D. Record a delivery issue as already occurred and apply the response for a missed Monday shipment.
Show answer and explanation

Response: C

Final answer: Record and validate the assumption, considering the related delivery risk.

Monday is an assumed delivery date. Record that premise and seek the supplier's confirmation, assessing the effect on testing if the device arrives late so the schedule reflects the uncertainty still present.

Question 51

An adaptive team delivers usable increments and expects feedback to refine its understanding of user needs. What role should requirements analysis play?

  • ☐ A. Use increment feedback to update status reports while preserving all original future requirement detail unchanged.
  • ☐ B. Finish requirements analysis before the first increment and use the later reviews only to confirm delivery against that initial detail.
  • ☐ C. Continue as work is refined and feedback informs the next product decisions.
  • ☐ D. Define upcoming acceptance conditions only after the corresponding increment has been delivered to its users.
Show answer and explanation

Response: C

Final answer: Continue as work is refined and feedback informs the next product decisions.

Usable increments give stakeholders something to evaluate. Their feedback can improve future product decisions. Continue eliciting and analyzing requirements, including the behavior and acceptance conditions needed for the next delivery.

Question 52

A team keeps a list of selected Product Backlog items and a delivery plan. A new Developer asks where to find the purpose that ties those items together for the current Sprint. Which component supplies that purpose?

  • ☐ A. The Product Goal associated with the Product Backlog.
  • ☐ B. The ordered Product Backlog items selected for the Sprint.
  • ☐ C. The Definition of Done associated with the Increment.
  • ☐ D. The Sprint Goal within the Sprint Backlog.
Show answer and explanation

Response: D

Final answer: The Sprint Goal within the Sprint Backlog.

The current Sprint's shared purpose is expressed by its Sprint Goal. Find it in the Sprint Backlog. That backlog also contains the selected Product Backlog items and the Developers' plan for delivering them.

Question 53

A team identifies a possible permit delay. Its probability and impact are estimated, and an owner is assigned to assess a response. Where should the associate document this uncertain event and the related information?

  • ☐ A. In the assumption log recording timely permit approval as a planning premise.
  • ☐ B. In the risk register
  • ☐ C. In the stakeholder register recording the permitting agency's role.
  • ☐ D. In the issue log describing a permit delay as an existing problem.
Show answer and explanation

Response: B

Final answer: In the risk register

The permit delay is uncertain. Its assessed probability, impact, owner and planned response work are details of an identified risk that the risk register keeps together for follow-up.

Question 54

Users find it hard to explain the desired screen layout, but they can react to examples. Which technique directly supports clarifying that requirement?

  • ☐ A. Create the full production screen from the analyst's interpretation before seeking user feedback.
  • ☐ B. Conduct another written questionnaire using the same layout questions the users have difficulty explaining.
  • ☐ C. Select a familiar layout from a previous product and ask users to approve it after implementation.
  • ☐ D. Review a suitable prototype with users and use their feedback to refine the requirement.
Show answer and explanation

Response: D

Final answer: Review a suitable prototype with users and use their feedback to refine the requirement.

Showing users a screen prototype gives them an example they can assess, and their comments on its layout help the team refine the requirement before committing to the production design.

Question 55

An associate is learning to maintain the issue log. The manager reviews the first entries, asks the associate to explain the classifications and gives specific feedback for the next update. Which role is being illustrated?

  • ☐ A. Instructor delivering a prepared lesson on the issue-log procedure.
  • ☐ B. Facilitator coordinating agreement among people with conflicting classifications.
  • ☐ C. Mentor providing long-term career guidance from personal experience.
  • ☐ D. Coach
Show answer and explanation

Response: D

Final answer: Coach

The manager uses the associate's actual issue-log decisions as material for guided practice. Questions about the classifications lead into specific feedback for the next update, illustrating coaching directed at improving performance on the task being learned.

Question 56

An activity has early start 5, early finish 9, late start 8 and late finish 12, all in elapsed working days. The earliest start of any immediate successor is 10. Using zero-lag finish-to-start relationships, what are its total float and free float?

  • ☐ A. Total float 1 day; free float 3 days.
  • ☐ B. Total float 7 days; free float 5 days.
  • ☐ C. Total float 4 days; free float 3 days.
  • ☐ D. Total float 3 days; free float 1 day.
Show answer and explanation

Response: D

Final answer: Total float 3 days; free float 1 day.

Total float is three days. Subtract the early start of 5 from the late start of 8 to calculate the allowance against the overall completion constraint. Now check the successor. Its earliest start is 10, leaving a one-day gap after this activity's early finish of 9, which is the free float under the supplied zero-lag finish-to-start relationship.

Question 57

The agreed project scope includes installing ten sensors and training the maintenance team. A proposal adds a customer analytics service that is outside those agreed deliverables. What should the associate identify?

  • ☐ A. A proposed scope addition that needs evaluation through the applicable change process.
  • ☐ B. A quality correction that brings the installed sensors into compliance with the agreed acceptance criteria.
  • ☐ C. Progressive elaboration that details the sensor installation already authorized by the scope.
  • ☐ D. An operational transition activity that supplies the maintenance training already included.
Show answer and explanation

Response: A

Final answer: A proposed scope addition that needs evaluation through the applicable change process.

The approved deliverables cover sensor installation and training. Adding the analytics service would expand that scope, so the proposed deliverable needs evaluation through the applicable change process. It can join the authorized work once the required decision has been made.

Question 58

Which TWO inputs should Developers consider when forecasting how much Product Backlog work they can complete in a coming Sprint?

  • ☐ A. Their past performance.
  • ☐ B. Their upcoming capacity.
  • ☐ C. An assumed full-time capacity figure that omits known absences and other commitments.
  • ☐ D. The sponsor's requested item count treated as a fixed delivery commitment.
  • ☐ E. Other teams' completed item counts used directly without checking comparability.
Show answer and explanation

Response: A, B

Final answer: Their upcoming capacity.; Their past performance.

The Developers know their upcoming availability. That capacity and their experience of completed work inform how much work they forecast for the Sprint.

Question 59

During a review, an associate notices that criticism of the estimate makes them defensive. They pause to identify their own reaction before responding. Which aspect of emotional intelligence is most directly illustrated?

  • ☐ A. Relationship management through negotiating agreement between the participants.
  • ☐ B. Self-awareness
  • ☐ C. Self-management through deliberate regulation of an outward response.
  • ☐ D. Social awareness through recognizing another participant's emotional state.
Show answer and explanation

Response: B

Final answer: Self-awareness

Identifying the defensive reaction and its trigger demonstrates self-awareness, the recognition step described before the associate decides how to respond to the criticism.

Question 60

Match each purpose to its record: 1. Link a requirement to its source and verification evidence; 2. Maintain an ordered list of evolving product work; 3. Describe actor-system interactions for a goal. Records: A. Use case; B. Requirements traceability matrix; C. Product Backlog. Use each once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--B; 2--C; 3--A

Final answer: 1--B; 2--C; 3--A

Use the requirement's source and verification links to identify the traceability matrix for 1-B. Ordered evolving product work locates 2-C in the Product Backlog, and the actor's goal and system interactions describe a use case for 3-A.

Question 61

A team first needs a broad set of possible ways to reduce packaging damage before comparing their feasibility. Which activity most directly supports that initial aim?

  • ☐ A. Require each participant to defend a complete business case before their idea enters the candidate list.
  • ☐ B. Score each suggestion against cost and feasibility immediately before inviting the next idea.
  • ☐ C. Rank the existing proposed solution first and collect ideas only for its implementation.
  • ☐ D. Generate candidate ideas without evaluating each one as it is suggested.
Show answer and explanation

Response: D

Final answer: Generate candidate ideas without evaluating each one as it is suggested.

The group is generating candidate ideas. Collect contributions before evaluating feasibility, giving suggestions room to enter the discussion without an immediate scoring decision or complete business-case defense.

Question 62

A team needs both clear requirements and coordinated delivery planning. Which statement best distinguishes the analyst's focus from the project manager's focus?

  • ☐ A. The analyst owns the overall delivery schedule, while the manager defines the detailed user requirements.
  • ☐ B. The analyst manages supplier assignments, while the manager independently resolves the meaning of every requirement.
  • ☐ C. The analyst supports understanding business needs and requirements, while the manager coordinates project delivery toward its objectives.
  • ☐ D. The analyst approves the business funding, while the manager obtains final product acceptance from users.
Show answer and explanation

Response: C

Final answer: The analyst supports understanding business needs and requirements, while the manager coordinates project delivery toward its objectives.

Clarifying requirements can affect the delivery plan. The analyst brings stakeholder needs into that discussion, and coordination with the project manager helps the team address the resulting scope or scheduling effects within its objectives.

Question 63

An agreed response calls for booking an alternate warehouse if the confirmed delivery forecast moves beyond Friday. The supplier now confirms Thursday, while the risk review shows that a further delay has become more likely. Which action is supported by these facts?

  • ☐ A. Update the risk owner with the Thursday forecast and changed likelihood, and continue monitoring the agreed trigger.
  • ☐ B. Book the alternate warehouse immediately because any increase in likelihood satisfies the Friday trigger.
  • ☐ C. Revise the trigger to Thursday without approval so the existing response can begin today.
  • ☐ D. Close the delivery risk because the confirmed forecast is still earlier than the trigger date.
Show answer and explanation

Response: A

Final answer: Update the risk owner with the Thursday forecast and changed likelihood, and continue monitoring the agreed trigger.

The forecast is Thursday. Notify the owner about it and the increased likelihood, continuing to monitor the agreed beyond-Friday threshold before initiating the triggered response.

Question 64

A release requires satisfaction of defined acceptance criteria and stakeholder acceptance under the agreed process. Which two results directly support readiness? Select two.

  • ☐ A. A release forecast approved before the acceptance evidence became available.
  • ☐ B. A completed activity checklist with the required acceptance tests still awaiting execution.
  • ☐ C. An implementation report confirming the features were built without the required acceptance decision.
  • ☐ D. The required stakeholder acceptance has been obtained through the agreed process.
  • ☐ E. Applicable evidence shows the required criteria are met.
Show answer and explanation

Response: D, E

Final answer: Applicable evidence shows the required criteria are met.; The required stakeholder acceptance has been obtained through the agreed process.

The scenario makes both acceptance evidence and agreed stakeholder acceptance prerequisites for release readiness. Select both. One establishes satisfaction of the criteria, and the other completes the required acceptance process.

Question 65

Match each activity to the process group that best describes its purpose. Activities: 1. Formally authorize a new project; 2. Develop the integrated plan; 3. Perform the planned project work; 4. Compare performance and address deviations; 5. Complete formal closure. Groups: A. Executing; B. Closing; C. Planning; D. Monitoring and Controlling; E. Initiating. Use each group once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--E; 2--C; 3--A; 4--D; 5--B

Final answer: 1--E; 2--C; 3--A; 4--D; 5--B

Formal project authorization corresponds to Initiating, establishing the first match as 1-E. Developing the plan gives 2-C. Execution accounts for performing the work in 3-A, with the comparison of performance and necessary corrective action assigned to Monitoring and Controlling in 4-D. Formal closure of responsibilities is Closing, which completes the response with 5-B.

Question 66

A sponsor identifies a business need, the project manager coordinates delivery, and users describe conflicting claim-processing rules. Which contribution most directly belongs to the business analyst's requirements role?

  • ☐ A. Set the overall project schedule independently of the manager and delivery team.
  • ☐ B. Elicit and analyze the rules with stakeholders to establish a shared, usable requirements description.
  • ☐ C. Authorize the additional funding before the sponsor reviews the business case.
  • ☐ D. Approve the delivered system on behalf of all users without their agreed acceptance process.
Show answer and explanation

Response: B

Final answer: Elicit and analyze the rules with stakeholders to establish a shared, usable requirements description.

Eliciting and analyzing the conflicting claim rules with stakeholders helps the analyst establish agreed behavior that the delivery team can implement.

Question 67

A sponsor funds short iterations but will not make any user representative available until the final release. The proposed product has uncertain usability requirements. Which concern should the associate raise?

  • ☐ A. Use team demonstrations to the sponsor as a complete replacement for feedback from people with usability knowledge.
  • ☐ B. Treat the short iteration cadence as evidence that the uncertain usability requirements are already being validated.
  • ☐ C. The team lacks timely customer feedback needed to resolve usability uncertainty during delivery.
  • ☐ D. Delay usability questions until final acceptance because the sponsor has approved incremental funding.
Show answer and explanation

Response: C

Final answer: The team lacks timely customer feedback needed to resolve usability uncertainty during delivery.

Arrange access to relevant users. Their evaluation of delivered interface behavior supplies the evidence needed to clarify uncertain requirements and inform subsequent iterations while development continues.

Question 68

A requirements workshop includes the project sponsor and developers but no representatives of the people who will process claims through the new system. What is the principal concern?

  • ☐ A. The developers should hold operational approval authority because they are present at the workshop.
  • ☐ B. The team may miss the operational needs and constraints of an affected user group.
  • ☐ C. The sponsor's attendance establishes that the claims processors' requirements have already been represented.
  • ☐ D. The workshop can settle the operational workflow now and obtain claims-processor feedback only after implementation.
Show answer and explanation

Response: B

Final answer: The team may miss the operational needs and constraints of an affected user group.

Claims processors know the work. Their missing operational perspective should enter the workshop before commitment so the workflow requirements reflect the activities and constraints the system must support.

Question 69

A few vocal participants dominate a problem-solving session. The facilitator wants each person's ideas recorded before group discussion. Which technique best fits?

  • ☐ A. Use an open brainstorm and invite quieter participants only after the initial debate has narrowed the proposals.
  • ☐ B. Ask the facilitator to shortlist solutions before participants vote on their preferred candidate.
  • ☐ C. Individual idea writing followed by round-robin sharing before discussion.
  • ☐ D. Hold an immediate anonymous vote on the first proposal and discuss alternatives only if it is rejected.
Show answer and explanation

Response: C

Final answer: Individual idea writing followed by round-robin sharing before discussion.

Writing ideas individually first gives each person a contribution in the candidate set, and sharing those recorded ideas in turn fits the requested nominal group technique before group discussion begins.

Question 70

Match each description with its earned-value measure. Descriptions: 1. Budgeted value of work scheduled by the reporting date; 2. Budgeted value of work actually accomplished; 3. Costs incurred for accomplished work; 4. Expected total cost when the defined scope is completed. Measures: A. Actual cost; B. Estimate at completion; C. Planned value; D. Earned value. Use each measure once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--C; 2--D; 3--A; 4--B

Final answer: 1--C; 2--D; 3--A; 4--B

Scheduled work at its budgeted value supplies planned value for 1-C. For 2-D, earned value measures accomplished work using the budget assigned to it. Use incurred expenditures for actual cost in 3-A, then the forecast total for estimate at completion in 4-B.

Question 71

A governing committee compares unrelated energy, education and transport initiatives, selecting investments that best support its strategic objectives. It does not coordinate them to produce a shared delivery benefit. Which concept best describes its selection activity?

  • ☐ A. Program delivery coordination
  • ☐ B. Routine operations scheduling
  • ☐ C. Portfolio management
  • ☐ D. Managing one project phase
Show answer and explanation

Response: C

Final answer: Portfolio management

The governing committee selects investments according to their contribution to strategic objectives, performing portfolio management across initiatives whose delivery benefits are independent of one another.

Question 72

In the current unconstrained network, a noncritical activity has 4 days of total float. Its duration increases by 2 days, with no other changes. Which conclusion is supported?

  • ☐ A. The delay can use 2 days of available total float without delaying the current project completion date.
  • ☐ B. The project completion date must move by 2 days.
  • ☐ C. The activity's immediate successors cannot be affected, regardless of its free float.
  • ☐ D. The activity gains 2 additional days of total float because its duration increased.
Show answer and explanation

Response: A

Final answer: The delay can use 2 days of available total float without delaying the current project completion date.

Two days of total float remain. Using two of the four float days keeps the current project finish within its stated limit in the unchanged network. Each immediate successor still needs its own network check.

Question 73

A requirements discussion produces an agreed exception-handling rule. What should the analyst record so implementation teams can use it accurately?

  • ☐ A. Record the original draft with a note that stakeholders discussed it, without incorporating the agreed rule.
  • ☐ B. Record the final behavior alone and omit the conditions that determine when the exception applies.
  • ☐ C. The agreed rule, relevant conditions and applicable decision or approval information.
  • ☐ D. Record the preferred implementation approach and let developers infer the exception rule from that design.
Show answer and explanation

Response: C

Final answer: The agreed rule, relevant conditions and applicable decision or approval information.

Record the agreed exception behavior. Include its application conditions and relevant approval information so implementation teams can reproduce the intended rule and identify when the exception applies.

Question 74

Which description identifies a work package in a project WBS?

  • ☐ A. A higher-level WBS element used to group and integrate several subordinate packages for control.
  • ☐ B. An individual schedule activity with defined relationships and dates, regardless of its position in the WBS.
  • ☐ C. A lowest-level portion of defined work for which cost, effort, duration and resources can be estimated and managed.
  • ☐ D. A future-work component retained above the detailed package level until later planning elaborates it.
Show answer and explanation

Response: C

Final answer: A lowest-level portion of defined work for which cost, effort, duration and resources can be estimated and managed.

The work package is the lowest WBS level at which cost, effort, duration and resources can be estimated and managed for the defined work.

Question 75

Read the three-panel comic. What should Omar do first?

Panel 1. Nia: The new weekend meetings clash with my caregivingarrangement.Panel 2. Omar: I thought the new time suited everyone.Panel 3. Nia: I did not have a chance to respond before it wasscheduled.

Scroll the diagram sideways on a narrow screen.

Diagram text description

Panel 1. Nia: The new weekend meetings clash with my caregiving arrangement. Panel 2. Omar: I thought the new time suited everyone. Panel 3. Nia: I did not have a chance to respond before it was scheduled.

  • ☐ A. Clarify Nia's availability and the team's coordination needs before reviewing the meeting arrangement.
  • ☐ B. Ask the other team members to vote on the current meeting time before clarifying Nia's constraints.
  • ☐ C. Keep the schedule for this cycle and ask Nia to document the effect at the next retrospective.
  • ☐ D. Arrange separate weekend attendance for Nia before checking how the team needs to coordinate.
Show answer and explanation

Response: A

Final answer: Clarify Nia's availability and the team's coordination needs before reviewing the meeting arrangement.

Nia has an availability constraint. Ask what prevents her attendance and establish the team's coordination needs before choosing a meeting adjustment that can work for the participants.

Question 76

Continue with Questions 76--150 using the remainder of the total 180-minute answering budget. Do not return to Questions 1--75.

The approved total budget is $120,000. Current CPI is 0.80. For this forecast, assume the current cost efficiency continues through the remaining work and the authorized scope stays unchanged. What estimate at completion follows that assumption?

  • ☐ A. $144,000
  • ☐ B. $120,000
  • ☐ C. $96,000
  • ☐ D. $150,000
Show answer and explanation

Response: D

Final answer: $150,000

Dividing the $120,000 budget at completion by CPI 0.80 gives a $150,000 estimate at completion. Apply the continuing-efficiency assumption. The forecast covers the same authorized scope using the cost efficiency already observed.

Question 77

A group is considering adaptive delivery for a product whose requirements will evolve. Which TWO proposed arrangements would directly support frequent learning and adjustment?

  • ☐ A. Regular access to users who can give feedback on working increments.
  • ☐ B. An empowered cross-functional team able to make day-to-day delivery decisions.
  • ☐ C. A central manager must approve each day-to-day adjustment before the team can act on increment feedback.
  • ☐ D. Each technical specialty completes its entire project-wide phase before the next specialty begins work.
  • ☐ E. User representatives attend final acceptance while the team uses initial assumptions for all interim decisions.
Show answer and explanation

Response: A, B

Final answer: Regular access to users who can give feedback on working increments.; An empowered cross-functional team able to make day-to-day delivery decisions.

Users can evaluate working increments. Their feedback supplies evidence about how the product should develop, and an empowered cross-functional team has the combined skills and day-to-day decision authority to use that evidence when adjusting its delivery work.

Question 78

Which TWO records directly support a meaningful earned-value status comparison for a work package?

  • ☐ A. Its authorized budget and planned work at the reporting date.
  • ☐ B. Reliable evidence of work accomplished and actual costs incurred for that work.
  • ☐ C. A revised work list that includes unauthorized additions while leaving the original performance baseline unchanged.
  • ☐ D. A cash-payment ledger used in place of incurred costs when performed work has not yet been invoiced.
  • ☐ E. A progress estimate set equal to the fraction of the budget spent, without independent evidence of completed work.
Show answer and explanation

Response: A, B

Final answer: Its authorized budget and planned work at the reporting date.; Reliable evidence of work accomplished and actual costs incurred for that work.

Gather the three earned-value inputs. The authorized budget and planned work define planned value at the reporting date, and reliable accomplishment evidence establishes the budgeted value earned, with incurred costs supplying actual cost for the same work package.

Question 79

Match each statement to its category: 1. A supplier may miss a future shipment; 2. A required shipment has already been missed; 3. Planning treats an unverified site-access estimate as true; 4. Installation may occur only during the approved shutdown. Categories: A. Constraint; B. Assumption; C. Issue; D. Risk. Use each category once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--D; 2--C; 3--B; 4--A

Final answer: 1--D; 2--C; 3--B; 4--A

The uncertain future shipment gives risk for 1-D. Record the already missed shipment as an issue for 2-C. The planning estimate accepted as true is an assumption for 3-B, and the shutdown requirement restricts installation as a constraint for 4-A.

Question 80

A proposed design revision reduces material cost but requires a longer installation and additional technician time. The sponsor asks for a decision recommendation. Which analysis best supports integration of the project plan?

  • ☐ A. Evaluate the combined scope, cost, schedule, resource and quality effects before recommending the decision.
  • ☐ B. Approve the cheaper materials now and ask the installation lead to absorb the additional time within the original dates.
  • ☐ C. Assess the longer installation first and retain the original cost forecast because the total scope has not changed.
  • ☐ D. Compare the material saving with added technician wages and defer the installation-date assessment until after approval.
Show answer and explanation

Response: A

Final answer: Evaluate the combined scope, cost, schedule, resource and quality effects before recommending the decision.

Installation will take longer. The design recommendation needs to account for the added technician effort and installation time along with the material saving, assessing the resulting effects across the integrated project plan before a decision is made.

Question 81

A regional organization coordinates separate laboratory, training and distribution projects to obtain service benefits that their independent management would not achieve. What does this coordinated arrangement describe?

  • ☐ A. The continuing operation of one laboratory
  • ☐ B. A program
  • ☐ C. A portfolio selected solely to balance investment across unrelated objectives
  • ☐ D. A work package within the laboratory project
Show answer and explanation

Response: B

Final answer: A program

Managing these separate projects together to obtain shared service benefits describes the coordinated program-management purpose, making a program the appropriate classification for the collection.

Question 82

During Sprint Planning, a Scrum Team learns that two Developers will be unavailable for half the coming Sprint. Recent Sprint delivery was achieved with everyone present. How should the Developers use that information when selecting work?

  • ☐ A. Reduce selection in exact proportion to headcount without considering item size, past performance or completion requirements.
  • ☐ B. Use the previous completed-item count unchanged and record the known absences only as a risk to that fixed selection.
  • ☐ C. Select the previous amount and ask the Product Owner to relax the completion standard to compensate for the absences.
  • ☐ D. Consider the reduced upcoming capacity along with past performance and the Definition of Done when forecasting the work.
Show answer and explanation

Response: D

Final answer: Consider the reduced upcoming capacity along with past performance and the Definition of Done when forecasting the work.

Two Developers have reduced availability. Their known absences change the capacity available for the coming Sprint, so the Developers need to use that capacity along with past performance and the Definition of Done when forecasting the work.

Question 83

A project delivers equipment expected to reduce operating cost over the following year. Which planning question is necessary to evaluate that benefit after the project ends?

  • ☐ A. Which equipment acceptance signature will replace the later operating-cost measurement?
  • ☐ B. Which approved project budget will be reported as the realized operating saving without a comparison of actual costs?
  • ☐ C. Which project completion date will be used as sufficient evidence that the entire annual saving was realized?
  • ☐ D. Who will measure the operating-cost result, when, and against which baseline?
Show answer and explanation

Response: D

Final answer: Who will measure the operating-cost result, when, and against which baseline?

To evaluate the expected operating-cost benefit, compare costs over the year following equipment delivery with the relevant baseline at agreed review times, assigning an owner to carry out that measurement.

Question 84

A work package has earned value of $24,000 and actual cost of $30,000. What does its cost performance index indicate?

  • ☐ A. A CPI of 0.80: the project is 80 percent complete regardless of its total budget.
  • ☐ B. A CPI of 1.25: the project will finish 25 percent earlier than planned.
  • ☐ C. A CPI of 0.80: $0.80 of budgeted work value was earned per $1.00 spent.
  • ☐ D. A CPI of 1.25: $1.25 of budgeted work value was earned per $1.00 spent.
Show answer and explanation

Response: C

Final answer: A CPI of 0.80: $0.80 of budgeted work value was earned per $1.00 spent.

The cost-efficiency result is 0.80. Dividing the $24,000 earned value by $30,000 actual cost produces that CPI, representing $0.80 of budgeted work value earned for each $1.00 spent on this work package.

Question 85

During a competitive procurement, a project team clarifies a mandatory interface requirement for one bidder. The clarification would affect how every bidder prices its proposal. All bidders are authorized to receive requirement information, and the submission deadline has not passed. What should the associate recommend?

  • ☐ A. Give the clarification only to bidders who independently ask the same question.
  • ☐ B. Wait until proposal scoring to explain the clarification to bidders whose price seems inconsistent.
  • ☐ C. Issue the material clarification through the approved channel to all eligible bidders.
  • ☐ D. Give the clarification to the lowest-priced bidder first so the team can estimate its cost effect.
Show answer and explanation

Response: C

Final answer: Issue the material clarification through the approved channel to all eligible bidders.

Use the approved common channel. The clarification changes a requirement relevant to pricing, so every eligible bidder authorized to receive it needs the information before the deadline to prepare comparable proposals.

Question 86

Match each question to its primary purpose: 1. Does the built behavior conform to the specified requirement? 2. Does the delivered solution meet the agreed business need? Purposes: A. Validation; B. Verification. Use each once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--B; 2--A

Final answer: 1--B; 2--A

Use the specified requirement for 1-B. Verification tests the built behavior for conformance to that requirement. For 2-A, use the agreed business need to validate the delivered solution.

Question 87

A project manager delegates collection of supplier progress data to an associate. Which understanding is appropriate?

  • ☐ A. The associate performs the assigned work, while delegation does not automatically transfer the manager's project-level responsibilities.
  • ☐ B. The supplier assumes the manager's project reporting responsibility because it provides the underlying data.
  • ☐ C. The manager may stop reviewing the progress information once its collection has been delegated.
  • ☐ D. The associate becomes responsible for every supplier decision because they now collect the progress information.
Show answer and explanation

Response: A

Final answer: The associate performs the assigned work, while delegation does not automatically transfer the manager's project-level responsibilities.

The associate has been assigned data collection, with the manager's project-level responsibilities remaining in their authorized roles unless an applicable arrangement expressly changes who holds them.

Question 88

Which two pieces of stakeholder information directly support planning requirements work? Select two.

  • ☐ A. The earliest submitted requirements draft treated as sufficient evidence of the stakeholder's expertise.
  • ☐ B. The most senior job title treated as the decision authority without checking assigned responsibilities.
  • ☐ C. Meeting attendance treated as confirmation that the person has approved the recorded requirements.
  • ☐ D. The stakeholder's relevant expertise and affected responsibilities.
  • ☐ E. The stakeholder's authority in the applicable requirement decisions.
Show answer and explanation

Response: D, E

Final answer: The stakeholder's relevant expertise and affected responsibilities.; The stakeholder's authority in the applicable requirement decisions.

Stakeholder responsibilities identify relevant expertise. Knowing that expertise helps the analyst select people who can contribute to requirements work, and checking their applicable decision authority establishes who can approve the decisions that work requires.

Question 89

A project faces a funding decision beyond the project manager's delegated authority. Which role provides resources and support and is accountable for enabling project success?

  • ☐ A. The business analyst, whose responsibility is to clarify the product requirements.
  • ☐ B. The supplier account manager, whose authority applies to the supplier's delivery commitments.
  • ☐ C. The project manager, whose delegated authority ends below the funding decision needed here.
  • ☐ D. The project sponsor
Show answer and explanation

Response: D

Final answer: The project sponsor

Funding exceeds the manager's authority. The sponsor provides project resources and support and is accountable for enabling project success, making that role responsible for addressing the funding decision described in this case.

Question 90

An analyst plans elicitation for a new service. Which two inputs directly support choosing participants and questions? Select two.

  • ☐ A. The relevant business need and agreed scope information.
  • ☐ B. A prepared survey reused without examining how its questions relate to the current business need.
  • ☐ C. A prior project's participant list copied without checking whether the current service has the same affected groups.
  • ☐ D. The existing sponsor-approved timeline treated as a substitute for identifying the people who understand the service.
  • ☐ E. Identification of affected stakeholders and their knowledge of the work.
Show answer and explanation

Response: A, E

Final answer: The relevant business need and agreed scope information.; Identification of affected stakeholders and their knowledge of the work.

Establish the business need and agreed scope, then identify affected stakeholders who can explain the service and help discover its requirements.

Question 91

A meeting's objective was to select one of two implementation options. Attendees discussed both, documented the agreed choice and assigned a due date and owner for the next action. Which evidence best supports judging the meeting effective?

  • ☐ A. It distributed complete presentation materials before the meeting, regardless of the result obtained.
  • ☐ B. It included detailed discussion of both options, even if the choice and follow-up had remained unresolved.
  • ☐ C. It followed the planned agenda sequence, regardless of whether a usable decision had been reached.
  • ☐ D. It achieved the decision objective and established actionable follow-up.
Show answer and explanation

Response: D

Final answer: It achieved the decision objective and established actionable follow-up.

Selecting an option and establishing a next action with an owner and due date supplies direct evidence that the meeting achieved its stated decision purpose and arranged usable follow-up.

Question 92

A predictive project has design, build and installation phases. A manager claims that monitoring and controlling can occur only after the build phase because it must be a separate product phase. Which explanation is correct?

  • ☐ A. Monitoring and controlling belongs only at the gate after each product phase, while work within the phase is execution alone.
  • ☐ B. Monitoring begins only when execution ends, because comparing performance requires all project work to be finished.
  • ☐ C. Management processes such as monitoring and controlling can occur throughout appropriate product phases.
  • ☐ D. Design, build and installation replace planning, executing and controlling, so no separate management purposes apply.
Show answer and explanation

Response: C

Final answer: Management processes such as monitoring and controlling can occur throughout appropriate product phases.

Monitoring and controlling can take place during design as the team checks progress and responds to deviations in that work. Continue those activities where appropriate through construction and installation. A product phase identifies the deliverable work underway, allowing management processes to serve that work throughout the phase.

Question 93

A testing activity requires 120 tester-hours within three working days. Each assigned tester can supply 6 productive hours per day, and work is divisible with no coordination loss. What is the minimum whole number of testers required?

  • ☐ A. 6 testers
  • ☐ B. 8 testers
  • ☐ C. 7 testers
  • ☐ D. 20 testers
Show answer and explanation

Response: C

Final answer: 7 testers

Each tester provides 18 productive hours. Three days at six hours per day gives that capacity, and dividing the required 120 hours by 18 yields about 6.67 under the stated divisible-work and no-loss assumptions. Whole-person staffing requires seven testers.

Question 94

An adaptive backlog item is scheduled for likely implementation next week but has no agreed acceptance criteria. What should the analyst support?

  • ☐ A. Assign the previous item's acceptance criteria and confirm their suitability only when this feature is demonstrated.
  • ☐ B. Clarify the item and its acceptance criteria with the relevant stakeholders and team before relying on it as ready.
  • ☐ C. Use the priority assigned by the Product Owner as confirmation that the missing success conditions are understood.
  • ☐ D. Select the item as ready and ask the testing team to infer acceptance criteria from the completed implementation.
Show answer and explanation

Response: B

Final answer: Clarify the item and its acceptance criteria with the relevant stakeholders and team before relying on it as ready.

Implementation is expected next week, so the team needs agreed behavior and success conditions now. Clarify the acceptance criteria with stakeholders and the team before treating the item as ready for selection.

Question 95

A delayed shipment was listed as a possible risk. The supplier now confirms that the shipment missed its required date. What should the associate recognize?

  • ☐ A. The event has occurred and now requires issue management as well as updating the related risk information.
  • ☐ B. Keep monitoring occurrence probability as the only needed action, without managing the confirmed consequences.
  • ☐ C. Close the risk entry and assume the related delivery problem is resolved because its occurrence is now certain.
  • ☐ D. Retain the entry solely as a future risk and postpone recording the actual delay until its final cost is known.
Show answer and explanation

Response: A

Final answer: The event has occurred and now requires issue management as well as updating the related risk information.

The shipment has been missed. Address this confirmed issue and its consequences, updating the related risk information as further effects become known, without waiting for the final cost to be established.

Question 96

Read the three-panel comic. What should the Product Owner and Developers do with the new information while the Sprint Goal remains viable?

Panel 1. Mara, Product Owner: The customer needs the export optionsooner than expected.Panel 2. Luis, Developer: We can still meet the Sprint Goal. Addingthe option may require changing which details we finish.Panel 3. Mara, Product Owner: The customer is asking whether we canmake the change during this Sprint.

Scroll the diagram sideways on a narrow screen.

Diagram text description

Panel 1. Mara, Product Owner: The customer needs the export option sooner than expected. Panel 2. Luis, Developer: We can still meet the Sprint Goal. Adding the option may require changing which details we finish. Panel 3. Mara, Product Owner: The customer is asking whether we can make the change during this Sprint.

  • ☐ A. Discuss its effect and renegotiate selected scope as needed while preserving the Sprint Goal.
  • ☐ B. Cancel the Sprint because any new request makes its original scope forecast invalid.
  • ☐ C. Let the Product Owner add the request to the Developers' plan before reviewing its effect on current work.
  • ☐ D. Preserve the selected scope unchanged and defer discussion of the new need until product completion.
Show answer and explanation

Response: A

Final answer: Discuss its effect and renegotiate selected scope as needed while preserving the Sprint Goal.

Luis says the Sprint Goal remains viable. Using the new export information, the Product Owner and Developers can discuss its effect and renegotiate selected work as needed, keeping that Goal intact.

Question 97

A team needs a shared description of how the project will be executed, monitored, controlled and closed, including the coordination of relevant subsidiary plans. Which document serves that purpose?

  • ☐ A. The product roadmap showing intended capabilities across releases.
  • ☐ B. The business case explaining the proposed investment's rationale.
  • ☐ C. The project charter authorizing the project and the manager's authority.
  • ☐ D. The project management plan
Show answer and explanation

Response: D

Final answer: The project management plan

The project management plan integrates subsidiary plans governing authorized project work.

Question 98

A recent mainline commit causes the automated integration build to fail. The cause is not immediately clear, and other Developers need a healthy shared codebase. What response best supports continuous integration?

  • ☐ A. Keep the mainline broken and direct Developers to maintain separate long-lived branches until the iteration ends.
  • ☐ B. Restore a working mainline promptly, such as by reverting the faulty commit, while investigating the failure.
  • ☐ C. Continue integrating unrelated changes into the failed mainline while diagnosing the original commit.
  • ☐ D. Disable the failed checks temporarily and use the displayed successful status as the team's integration result.
Show answer and explanation

Response: B

Final answer: Restore a working mainline promptly, such as by reverting the faulty commit, while investigating the failure.

The faulty commit has broken the shared mainline, so other Developers cannot rely on the build for integration. Restore a working codebase promptly, for example by reverting the commit while investigating it. Keep the checks active.

Question 99

Before authorizing a project, leaders want to understand the business need, viable options and expected value. Which document most directly supports that justification?

  • ☐ A. The project management plan describing how authorized work will be managed.
  • ☐ B. The business case
  • ☐ C. The benefits measurement record describing results already achieved after delivery.
  • ☐ D. The project charter defining authorization and the project manager's authority.
Show answer and explanation

Response: B

Final answer: The business case

A business case examines the proposed investment before leaders authorize a project, using the business need to evaluate possible responses and the value each could produce.

Question 100

A delivery breakdown includes account creation, profile editing and preference settings. The team wants an initial usable result for invited users. Which iteration scope best supports that purpose?

  • ☐ A. Build the complete database layer for all three features and defer the user interface until the next iteration.
  • ☐ B. Build all three interfaces against simulated data and defer actual account creation to a later release.
  • ☐ C. Allocate equal effort to each feature's technical components without checking for a complete usable path.
  • ☐ D. A small account-creation path with the implementation and checks needed for invited users to use it.
Show answer and explanation

Response: D

Final answer: A small account-creation path with the implementation and checks needed for invited users to use it.

Invited users must be able to complete account creation. Select a small scope that connects the necessary technical components and checks into that working path, producing a usable outcome within the first delivery.

Question 101

A geographically distributed team will replace a known reporting system using approved stable requirements and an established migration procedure. Which factor most directly supports predictive planning?

  • ☐ A. The need to coordinate reporting times across several local working days.
  • ☐ B. The geographical separation of the people assigned to the migration.
  • ☐ C. The availability of shared collaboration tools for remote status meetings.
  • ☐ D. The stable defined requirements and understood delivery method.
Show answer and explanation

Response: D

Final answer: The stable defined requirements and understood delivery method.

The migration procedure is established. Approved stable requirements define the intended replacement, giving the team enough understanding of both the result and its delivery method to plan the work before execution using a predictive approach.

Question 102

A project arranges supplier insurance for a specified financial exposure and separately performs preventive testing to reduce defect probability. Which statement distinguishes the responses?

  • ☐ A. Insurance accepts the full exposure internally, while preventive testing shifts financial responsibility to the insurer.
  • ☐ B. Insurance avoids the underlying defect event, while preventive testing accepts its probability unchanged.
  • ☐ C. Insurance addresses transfer of the specified exposure, while preventive testing mitigates defect probability.
  • ☐ D. Insurance mitigates defect probability, while preventive testing transfers the resulting financial exposure.
Show answer and explanation

Response: C

Final answer: Insurance addresses transfer of the specified exposure, while preventive testing mitigates defect probability.

The contract allocates the specified financial exposure to the insurer, establishing transfer under its terms. Follow the preventive-testing action too. Finding defects before delivery supports the project's mitigation of defect probability.

Question 103

A Scrum Team's Definition of Done requires security testing. One item is coded and functionally tested, but its security testing is unfinished at the Sprint's end. What is its status under that Definition of Done?

  • ☐ A. It is not part of a usable Increment meeting the Definition of Done and returns to the Product Backlog for future consideration.
  • ☐ B. It is part of the Increment if the Product Owner accepts the unfinished testing as a future task.
  • ☐ C. It is part of the Increment because coding and functional tests account for most of its work.
  • ☐ D. It becomes part of the Increment when stakeholders see it at the Sprint Review, even without the required testing.
Show answer and explanation

Response: A

Final answer: It is not part of a usable Increment meeting the Definition of Done and returns to the Product Backlog for future consideration.

Required security testing is missing. Until that testing satisfies the Definition of Done, the item cannot enter the usable Increment or be presented as complete at Sprint Review, and it returns to the Product Backlog.

Question 104

A quiet team member stops contributing after a change in working hours. The manager wants to understand the reason before proposing a remedy. Which response best supports that aim?

  • ☐ A. Ask the entire team for possible explanations and select the most common account before speaking with the member.
  • ☐ B. Ask the member privately about the change and listen to their explanation.
  • ☐ C. Send a teamwide reminder about participation before discussing the individual's circumstances.
  • ☐ D. Reassign the member to a quieter task and use their later performance to infer whether the working-hours change mattered.
Show answer and explanation

Response: B

Final answer: Ask the member privately about the change and listen to their explanation.

Ask privately and listen. The member's account of the changed circumstances supplies information the manager needs to understand the situation before proposing a remedy.

Question 105

A developer using test-driven development has written a test for a small new behavior and confirmed that it fails. What is the next step in the usual cycle?

  • ☐ A. Refactor the existing design first while leaving the new behavioral test failing.
  • ☐ B. Change the expected result to match the current implementation without adding the required behavior.
  • ☐ C. Expand the failing test to cover the remaining features before implementing the small behavior.
  • ☐ D. Write the functional code needed to make the test pass.
Show answer and explanation

Response: D

Final answer: Write the functional code needed to make the test pass.

The failing test identifies the next small behavior to implement. Write enough code to make it pass. Once that behavior works, the usual test-driven development cycle allows refactoring with the passing tests maintained.

Question 106

A quality objective is stated as Make the scan service fast. Which revision gives the team an objectively checkable requirement?

  • ☐ A. The scan service should respond promptly during the busiest part of the working day.
  • ☐ B. At least 95% of scans must return a result within two seconds under the specified test load.
  • ☐ C. The scan service should reduce waiting enough for staff to complete their usual daily workload.
  • ☐ D. The scan service should match the speed users expect from comparable products.
Show answer and explanation

Response: B

Final answer: At least 95% of scans must return a result within two seconds under the specified test load.

Test scans under the specified load and measure how often a result arrives within two seconds. The requirement sets a 95-percent minimum. Those defined conditions allow the team to compare observed response times with the agreed target and determine whether the service meets it.

Question 107

A zero-lag, finish-to-start network begins with A, which takes 3 days. B and C both follow A and take 5 and 8 days, respectively. D takes 2 days and follows both B and C. Resources are unconstrained, all days are working days, and no external dates apply. What is the planned project duration?

  • ☐ A. 13 days
  • ☐ B. 10 days
  • ☐ C. 8 days
  • ☐ D. 18 days
Show answer and explanation

Response: A

Final answer: 13 days

The project takes thirteen working days. A finishes at day 3, B then finishes at day 8 and C at day 11, so D starts only after both are available and finishes two days later. A--C--D is the controlling path.

Question 108

Read the comic. Which release scope satisfies both stated customer goals within the available capacity?

Panel 1. Rafi: Customers need refunds and shipment tracking in thisrelease. We have ten team-days.Panel 2. Zoe: Refunds need six days and tracking needs four. Refundsrequire identity verification.Panel 3. Rafi: Verification is already usable. Rebuilding it wouldtake seven days.

Scroll the diagram sideways on a narrow screen.

Diagram text description

Panel 1. Rafi: Customers need refunds and shipment tracking in this release. We have ten team-days. Panel 2. Zoe: Refunds need six days and tracking needs four. Refunds require identity verification. Panel 3. Rafi: Verification is already usable. Rebuilding it would take seven days.

  • ☐ A. Rebuild verification and deliver tracking, leaving refunds for a later release.
  • ☐ B. Deliver refunds alone and postpone tracking even though its effort fits the remaining capacity.
  • ☐ C. Rebuild verification and deliver refunds, reserving shipment tracking for a later release.
  • ☐ D. Deliver refunds and shipment tracking, using the existing verification capability.
Show answer and explanation

Response: D

Final answer: Deliver refunds and shipment tracking, using the existing verification capability.

Refunds can use the verification capability that is already available. Select refunds and tracking. Together they satisfy both customer goals with ten team-days of effort, fitting the capacity and the refund dependency shown.

Question 109

The agreed governance procedure gives the project manager authority for cost changes up to $5,000. Larger changes require sponsor review. A supported forecast shows an $8,000 change. What should the associate recommend?

  • ☐ A. Prepare the evidence and route the change for the required sponsor review.
  • ☐ B. Implement the forecast change before review because evidence of the amount establishes approval.
  • ☐ C. Ask the project manager to authorize the amount now and obtain sponsor confirmation at the next routine report.
  • ☐ D. Divide the same supported change between cost accounts so each entry is within the manager's limit.
Show answer and explanation

Response: A

Final answer: Prepare the evidence and route the change for the required sponsor review.

Prepare the change evidence for sponsor review under the agreed procedure, which assigns the $8,000 cost-change decision to that review route. The project manager's delegated approval stops at $5,000.

Question 110

A company is replacing its supplier-ordering portal. Which person is an external stakeholder relative to that company?

  • ☐ A. A representative employed by a supplier that receives orders through the portal.
  • ☐ B. A warehouse employee of the company
  • ☐ C. The company's procurement manager
  • ☐ D. The company's internal IT support lead
Show answer and explanation

Response: A

Final answer: A representative employed by a supplier that receives orders through the portal.

The supplier representative is external. That person works outside the company and is affected by receiving orders through its portal.

Question 111

A project is intended to reduce average processing time from ten minutes to six minutes within three months of adoption. Which two elements support evaluating that benefit? Select two.

  • ☐ A. The project budget spent used as proof that the expected time saving has been achieved.
  • ☐ B. A defined owner and measurement date for the operating result.
  • ☐ C. Comparable processing-time data before and after adoption.
  • ☐ D. The project's completed-task count used as a substitute for operating-time data.
  • ☐ E. The approved deployment date used as the measurement of the later processing-time result.
Show answer and explanation

Response: B, C

Final answer: A defined owner and measurement date for the operating result.; Comparable processing-time data before and after adoption.

Collect comparable processing-time observations before adoption and at the three-month measurement date to evaluate the proposed reduction from ten minutes to six. Assign responsibility for that measurement. The named owner can examine the operating result against the intended benefit using the data collected at those points.

Question 112

A reset link must expire 20 minutes after issue and cannot be reused after a successful reset. A link issued at 10:00 is used successfully at 10:12. Which expected test result matches both rules?

  • ☐ A. Accept another use at 10:15 and reject an unused link of the same issue time at 10:21.
  • ☐ B. Accept another use at 10:15 and accept an unused link of the same issue time at 10:21.
  • ☐ C. Reject another use at 10:15 and accept an unused link of the same issue time at 10:21.
  • ☐ D. Reject another use at 10:15 and reject an unused link of the same issue time at 10:21.
Show answer and explanation

Response: D

Final answer: Reject another use at 10:15 and reject an unused link of the same issue time at 10:21.

Successful use at 10:12 ends the first link's permitted use, requiring rejection of its 10:15 retry, and the unused link issued at 10:00 expires at 10:20, requiring rejection of its 10:21 attempt.

Question 113

In a predictive project, a formally approved change adds a required deliverable and its authorized budget. The team starts the approved work, but the status system still compares progress against the old scope and budget. What should the associate recommend?

  • ☐ A. Keep the old plan permanently so the approved extra work always appears as a variance.
  • ☐ B. Use the new budget without recording the approval or changed scope.
  • ☐ C. Incorporate the approved change into the controlled plan and relevant status records before using them for the updated comparison.
  • ☐ D. Remove actual costs of the new deliverable from the report to preserve the original comparison.
Show answer and explanation

Response: C

Final answer: Incorporate the approved change into the controlled plan and relevant status records before using them for the updated comparison.

The deliverable and additional budget have formal approval. Update the controlled plan and status records to use that authorized scope as the reporting basis, so subsequent progress and cost comparisons reflect the approved work.

Question 114

At the Daily Scrum, Developers find that a testing bottleneck threatens the Sprint Goal. Which TWO actions fit the purpose of this event?

  • ☐ A. Inspect progress toward the Sprint Goal.
  • ☐ B. Change the Definition of Done during the event to count unfinished tests as completed work.
  • ☐ C. Adapt the upcoming work plan to address the bottleneck.
  • ☐ D. Replace the goal inspection with a utilization report sent to an outside manager.
  • ☐ E. Use the event to obtain individual task assignments from the Product Owner.
Show answer and explanation

Response: A, C

Final answer: Inspect progress toward the Sprint Goal.; Adapt the upcoming work plan to address the bottleneck.

Developers inspect progress toward the Sprint Goal and adapt their plan in the Daily Scrum, so examining that progress and adjusting upcoming work addresses the testing bottleneck within the event's purpose.

Question 115

The only planned meeting item is to distribute an already approved installation date. No discussion or joint decision is needed, and everyone can access the notification system. What is the most suitable communication choice?

  • ☐ A. Ask each recipient to confirm the date in a separate conversation before issuing the notice.
  • ☐ B. Send the approved date through the appropriate notification channel.
  • ☐ C. Hold a short full-team meeting because approved dates should always be distributed synchronously.
  • ☐ D. Wait for the next decision meeting and include the date with that meeting's discussion items.
Show answer and explanation

Response: B

Final answer: Send the approved date through the appropriate notification channel.

Everyone can access the notification channel. Send the approved date through it to provide the settled information to the intended recipients, following the communication purpose stated in the scenario.

Question 116

Match each Sprint Planning concern with its appropriate description. Use each description once: 1. The purpose of this Sprint; 2. What can be done this Sprint; 3. How selected work will get done. Descriptions: A. Developers create the plan needed to produce the Increment; B. The Scrum Team establishes a useful Sprint Goal; C. Developers select items through discussion with the Product Owner.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--B; 2--C; 3--A

Final answer: 1--B; 2--C; 3--A

The Scrum Team establishes the Sprint Goal during Sprint Planning, giving 1-B. Developers select the work through discussion with the Product Owner and create the plan for delivering the Increment, completing 2-C and 3-A.

Question 117

A project team develops a high-level plan from early information. After a site survey, it can estimate installation activities more accurately. The agreed planning approach allows later detail without changing the authorized objectives. What should the team do?

  • ☐ A. Freeze the early activity estimates until the project ends because elaboration would alter the planning record.
  • ☐ B. Elaborate the plan using the new information while applying control to any actual baseline changes.
  • ☐ C. Replace the authorized objectives with the site-survey findings before checking whether they change the intended work.
  • ☐ D. Update every approved baseline immediately on receiving the survey, without the applicable review.
Show answer and explanation

Response: B

Final answer: Elaborate the plan using the new information while applying control to any actual baseline changes.

The survey improves the estimates. Use its information to elaborate installation planning within authorized objectives, following the applicable control procedure if an update changes an approved baseline.

Question 118

Users cannot yet agree on the best search filters for a new catalog. They can attend short demonstrations and try working versions. The team can change the software without replacing physical equipment. Which approach best supports learning about those filters?

  • ☐ A. Deliver small working increments and use user feedback to adjust subsequent work.
  • ☐ B. Write detailed weekly completion reports and defer product demonstrations until release.
  • ☐ C. Let each developer choose the filters independently and integrate them at the end.
  • ☐ D. Finalize every filter before users try the product, then deliver the complete catalog.
Show answer and explanation

Response: A

Final answer: Deliver small working increments and use user feedback to adjust subsequent work.

The users are still discovering which search filters help them. Small working increments let them try actual behavior and give feedback that the team can use to adjust later deliveries while changes remain practical.

Question 119

At the end of a requirements meeting, different attendees describe different versions of the decision. What should the facilitator do before closing?

  • ☐ A. Restate the proposed decision and confirm the agreed result and next steps with the participants.
  • ☐ B. Record all versions as approved alternatives and let developers choose the one they can implement fastest.
  • ☐ C. Publish the facilitator's preferred account and invite corrections after implementation begins.
  • ☐ D. Use the most senior attendee's account as the agreed decision without confirming it with the group.
Show answer and explanation

Response: A

Final answer: Restate the proposed decision and confirm the agreed result and next steps with the participants.

Confirm the meeting's decision. Restate the proposed result and check it with the participants, including the next steps they will take, so the group has an agreed account before the meeting closes.

Question 120

In a SAFe Agile Release Train, someone needs to guide participants through PI Planning and help the train improve the flow of value through its events. Which role has that responsibility?

  • ☐ A. Product Management, acting as the content authority for the train's product direction.
  • ☐ B. System Architect, providing the technical architecture and interface direction.
  • ☐ C. A team Scrum Master, supporting the effectiveness of one Agile Team.
  • ☐ D. Release Train Engineer.
Show answer and explanation

Response: D

Final answer: Release Train Engineer.

The Release Train Engineer coordinates train-level events such as PI Planning and supports the flow of value across the Agile Release Train.

Question 121

A manager wants to handle tense stakeholder discussions more effectively. Which two practices directly support emotional intelligence? Select two.

  • ☐ A. Let the most senior participant define the manager's response before examining the concerns raised.
  • ☐ B. Recognize personal emotional triggers before responding.
  • ☐ C. Interpret a quiet response as agreement and close the discussion without checking understanding.
  • ☐ D. Treat the strength of the initial emotional reaction as sufficient evidence that the other person intends harm.
  • ☐ E. Listen to understand the other person's concerns and perspective.
Show answer and explanation

Response: B, E

Final answer: Recognize personal emotional triggers before responding.; Listen to understand the other person's concerns and perspective.

Recognize the emotional trigger. Understanding that reaction and listening to the stakeholder's concerns gives the manager awareness of the situation before choosing a considered response.

Question 122

The project role agreement assigns approval of permanent changes to the invoice process to the process owner. The process manager monitors day-to-day performance, and the analyst documents proposed changes. Who approves a permanent change under this agreement?

  • ☐ A. The software supplier solely because the change requires configuration
  • ☐ B. The process owner
  • ☐ C. The analyst solely because the proposed change is documented
  • ☐ D. The process manager solely because daily results are monitored
Show answer and explanation

Response: B

Final answer: The process owner

The role agreement assigns permanent process-change approval to the process owner, giving the analyst the stated decision right needed to identify the authorized approver for this change.

Question 123

Match each planning question to its most direct record: 1. How will project communications be managed? 2. What is the product direction across future releases? 3. What approved time-phased budget will project costs be compared with? Records: A. Product roadmap; B. Cost baseline; C. Communications management plan. Use each once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--C; 2--A; 3--B

Final answer: 1--C; 2--A; 3--B

Use the communications management plan for how project information is handled, matching 1-C. The roadmap gives future release direction, completing 2-A, and the approved time-phased budget for cost comparisons is the cost baseline, completing 3-B.

Question 124

An analyst wants comparable responses from 600 geographically dispersed users about which of six known reporting problems occurs most often. Which approach is most suitable?

  • ☐ A. Unstructured interviews with a few available users, used as the frequency estimate for all 600.
  • ☐ B. Observation of one user's workday, used as the comparable response for the whole dispersed group.
  • ☐ C. A facilitated workshop with one department, used to rank the frequency for users in every location.
  • ☐ D. A clearly designed survey of the relevant users.
Show answer and explanation

Response: D

Final answer: A clearly designed survey of the relevant users.

Six hundred dispersed users need to report how often they encounter six known problems. A survey suits that comparison. Clearly designed common questions can collect the comparable frequency reports the analyst needs from that population.

Question 125

Which statement correctly distinguishes the project manager from the sponsor?

  • ☐ A. The manager transfers project accountability to the sponsor whenever an unresolved delivery issue occurs.
  • ☐ B. The manager leads the project team toward its objectives, while the sponsor provides resources and support to enable success.
  • ☐ C. The manager defines user acceptance independently, while the sponsor maintains all detailed activity estimates.
  • ☐ D. The manager authorizes the organization's investment, while the sponsor coordinates every daily team assignment.
Show answer and explanation

Response: B

Final answer: The manager leads the project team toward its objectives, while the sponsor provides resources and support to enable success.

Leading the team toward the delivery objectives is the project manager's responsibility, supported by the sponsor's provision of resources and support. Their coordination helps direct project issues to the appropriate authority.

Question 126

A changed customer identifier affects both the registration and reporting teams. What should the analyst communicate?

  • ☐ A. Send the new identifier to registration and rely on reporting to infer the change from the next generated data file.
  • ☐ B. The agreed change and its relevant effects to both teams through the defined coordination process.
  • ☐ C. Send the detailed change to reporting after registration has implemented it, without coordinating the shared transition.
  • ☐ D. Notify both teams that a requirement changed without describing the identifier behavior or affected interfaces.
Show answer and explanation

Response: B

Final answer: The agreed change and its relevant effects to both teams through the defined coordination process.

The identifier links registration and reporting. Communicate the agreed change and relevant behavior to both teams through the defined coordination process early enough for them to keep implementation and transition compatible.

Question 127

A project WBS covers the delivered equipment but omits a required operator-training deliverable included in the approved scope. The schedule was built only from that WBS. What should the associate identify?

  • ☐ A. A scope-coverage gap that needs to be addressed before treating the schedule as complete.
  • ☐ B. Proof that training is outside scope because it is absent from the WBS.
  • ☐ C. A reason to remove training from the approved scope without change review.
  • ☐ D. A complete schedule because equipment delivery is the only work that needs planning.
Show answer and explanation

Response: A

Final answer: A scope-coverage gap that needs to be addressed before treating the schedule as complete.

Include the approved operator-training deliverable. Bringing that authorized work into the WBS closes the scope-coverage gap and lets the team incorporate its activities into the schedule built from the breakdown.

Question 128

The analyst sends a revised requirement to two implementation teams. What provides the strongest evidence that they understand the changed behavior consistently?

  • ☐ A. Count the reviewers who opened the document and use the highest readership figure as confirmation.
  • ☐ B. Ask each team to explain the expected behavior using the agreed examples and resolve differences.
  • ☐ C. Ask each team to approve the document title without discussing examples of the changed behavior.
  • ☐ D. Obtain written acknowledgment that both teams received the revision and treat receipt as consistent understanding.
Show answer and explanation

Response: B

Final answer: Ask each team to explain the expected behavior using the agreed examples and resolve differences.

Check understanding through the teams' examples. Each team's explanation reveals how it expects the changed behavior to work, giving the analyst evidence for resolving interpretation issues before either implementation relies on them.

Question 129

A project will replace paper purchase approvals with an electronic workflow. Which outcome best represents the organizational change the project is intended to enable?

  • ☐ A. The project's technical acceptance record is signed while employees have not yet adopted the workflow.
  • ☐ B. The electronic workflow is deployed while purchasing decisions continue through the old paper process.
  • ☐ C. Employees consistently use the new approval process to make purchasing decisions.
  • ☐ D. The new training materials are complete while the intended operating process remains unchanged.
Show answer and explanation

Response: C

Final answer: Employees consistently use the new approval process to make purchasing decisions.

Consistent purchasing decisions through the new electronic workflow show that people have adopted the process, providing observed operational evidence of the organizational change requested in the question.

Question 130

A Scrum Team finds in its retrospective that slow review of small changes repeatedly delays usable delivery. The team agrees that assigning a rotating reviewer and checking turnaround could help. What should it do with this finding?

  • ☐ A. Use the retrospective only to identify the slowest reviewer and leave the agreed process unchanged.
  • ☐ B. Change the review arrangement without monitoring turnaround because agreement already proves the improvement.
  • ☐ C. Implement an actionable improvement and inspect whether review turnaround improves.
  • ☐ D. Record the reviewer proposal and defer trying it until the team has completed the entire product.
Show answer and explanation

Response: C

Final answer: Implement an actionable improvement and inspect whether review turnaround improves.

Try the agreed rotating-reviewer arrangement and check its effect on the turnaround obstacle identified in the retrospective. Evaluate what changes in delivery. The results will support a decision about retaining or adjusting the improvement.

Question 131

A requirement changes from allowing one address to allowing several addresses per account. The team maintains links from that requirement to design elements and test cases. What should the analyst use those links to identify?

  • ☐ A. Update the requirement wording and defer examination of its linked design and tests until final acceptance.
  • ☐ B. Design and test evidence that may need review because of the changed requirement.
  • ☐ C. Treat each linked design element as an automatically approved scope addition.
  • ☐ D. Use the old passing results to verify the changed behavior without reviewing the tests they link to.
Show answer and explanation

Response: B

Final answer: Design and test evidence that may need review because of the changed requirement.

The address requirement has changed to support multiple addresses. Its traceability links identify design and test evidence that may need revision, allowing the analyst to assess those impacts. Check the linked evidence for conformance to the updated behavior.

Question 132

A Product Owner is ordering two ready items for a release whose agreed objective is to recover lost completed purchases. One repairs a checkout failure affecting many paying users. The other adds a bulk export that saves internal analysts time on weekly reporting. The effort is similar, and no dependency or mandatory deadline favors either item. Which ordering is best supported?

  • ☐ A. Place the export first because its internal time saving should take precedence without considering the purchase objective.
  • ☐ B. Give the items equal priority because similar effort establishes equal contribution to the release objective.
  • ☐ C. Place the checkout repair first because it directly supports the stated release objective.
  • ☐ D. Use request arrival order as the sole rule even though the items contribute differently to the agreed objective.
Show answer and explanation

Response: C

Final answer: Place the checkout repair first because it directly supports the stated release objective.

Repairing checkout addresses the failed purchases that the release is meant to recover. Place that repair first. Its effect on the agreed objective gives the Product Owner a reason for this ordering under the equal-effort and dependency conditions.

Question 133

A project coordinator is assigned to score software proposals. One bidder has offered the coordinator a paid weekend consulting role beginning after the purchase. The coordinator has not accepted the offer. Scoring starts tomorrow, and a qualified replacement is available. What should the coordinator do before participating in the decision?

  • ☐ A. Ask a teammate to check the completed scores, then disclose the offer before the final award.
  • ☐ B. Decline the consulting offer privately, complete the scoring, and disclose it when the award is announced.
  • ☐ C. Disclose the offer to the appropriate stakeholders and refrain from influencing the decision until the conflict is appropriately resolved.
  • ☐ D. Disclose the offer but continue scoring while stakeholders decide whether mitigation is needed.
Show answer and explanation

Response: C

Final answer: Disclose the offer to the appropriate stakeholders and refrain from influencing the decision until the conflict is appropriately resolved.

The paid offer creates a competing interest for the award decision. Disclose it to the appropriate stakeholders. Refrain from influencing the award until the conflict is appropriately resolved, using the available replacement as needed.

Question 134

A Scrum Team is building the eligibility report needed for a proposed service. The organization withdraws the service, and the Product Owner confirms that the current Sprint Goal is obsolete. Who has authority to cancel this Sprint?

  • ☐ A. The Developers collectively, because they own the selected delivery plan.
  • ☐ B. The project sponsor directly, because withdrawing the service transfers Scrum cancellation authority to the sponsor.
  • ☐ C. The Scrum Master, because facilitating Scrum events includes authority to cancel any Sprint.
  • ☐ D. The Product Owner
Show answer and explanation

Response: D

Final answer: The Product Owner

The Sprint Goal is obsolete. Under the Scrum Guide, the Product Owner has authority to cancel the Sprint when its Goal becomes obsolete, which applies after withdrawal of the service makes the planned eligibility report unnecessary.

Question 135

Testing has verified 80 of 100 agreed acceptance checks. The remaining 20 checks have not been run, and their results are unknown. A sponsor asks whether all acceptance checks have passed. Which answer gives the most accurate account?

  • ☐ A. The product failed acceptance because twenty checks have not produced passing results.
  • ☐ B. Eighty checks passed; the remaining twenty are untested, so completion of all acceptance checks is not yet established.
  • ☐ C. Acceptance is almost complete, so no further detail is needed for the sponsor to assess readiness.
  • ☐ D. The product passed acceptance because every check performed so far succeeded.
Show answer and explanation

Response: B

Final answer: Eighty checks passed; the remaining twenty are untested, so completion of all acceptance checks is not yet established.

Report the actual acceptance-check status. The verified results cover eighty checks, with twenty still awaiting execution and therefore supplying no result that could establish completion of the entire required set.

Question 136

A Kanban team's workflow defines an item as started when implementation begins and finished when production deployment is complete. An item was requested on day 1, started implementation on day 4, and finished deployment on day 10. Using elapsed days without inclusive counting, what is its cycle time?

  • ☐ A. 9 days
  • ☐ B. 4 days
  • ☐ C. 6 days
  • ☐ D. 10 days
Show answer and explanation

Response: C

Final answer: 6 days

From implementation on day 4 through deployment on day 10, the item takes six elapsed days of cycle time under the team's defined start and finish boundaries. The request predates implementation.

Question 137

Two implementation teams work different shifts and need the exact approved interface specification and its change record. There is no unresolved dispute. The agreed communication procedure uses a version-controlled repository accessible to both teams, with questions handled through a named analyst. Which action best fits this need?

  • ☐ A. Send each team an editable private copy without the shared version identifier or change record.
  • ☐ B. Send a short change summary instead of the approved specification and let each team infer the exact interface details.
  • ☐ C. Schedule a live briefing that only one shift can attend and treat that attendance as distribution to both teams.
  • ☐ D. Publish the approved version and change record in the agreed repository, notify both teams and provide the route for questions.
Show answer and explanation

Response: D

Final answer: Publish the approved version and change record in the agreed repository, notify both teams and provide the route for questions.

The agreed repository gives both shifts access to the same approved specification and change history. Notification tells each team where that authoritative version is available, while the named analyst handles implementation questions through the established communication procedure.

Question 138

Match each measurement to its Kanban flow metric. Measurements: 1. Count of started, unfinished items; 2. Count of items finished per week; 3. Elapsed time from start until finish; 4. Elapsed time since an unfinished item started. Metrics: A. Cycle time; B. Work item age; C. WIP; D. Throughput. Use each metric once.

Write the matching letter for each numbered prompt.

Show answer and explanation

Response: 1--C; 2--D; 3--A; 4--B

Final answer: 1--C; 2--D; 3--A; 4--B

Start with the unfinished-item count. It identifies WIP for 1-C, and weekly completions give throughput for 2-D. Use the recorded start and finish timestamps to obtain cycle time for 3-A, then measure an unfinished item's elapsed time to the present for work item age and 4-B.

Question 139

Two specialists disagree about a proposed installation sequence. The manager asks each to explain the supporting constraints and helps them compare feasible options against the project objective. Which role is the manager primarily exercising?

  • ☐ A. Sponsor authorizing additional funding for the chosen installation work.
  • ☐ B. Coach helping one specialist develop a personal skill through individual feedback.
  • ☐ C. Facilitator
  • ☐ D. Technical decision maker independently selecting the installation sequence for the specialists.
Show answer and explanation

Response: C

Final answer: Facilitator

Guiding the specialists as they explain constraints and assess feasible options helps their discussion advance toward the project objective, demonstrating facilitation with the technical selection left to the appropriate participants.

Question 140

The project quality plan requires a documented sample inspection before a production batch is released. The batch is ready, but its required inspection has not occurred. No approved exception exists. What should the associate recommend?

  • ☐ A. Release the batch now and complete the required inspection as a post-release check to protect the delivery date.
  • ☐ B. Ask the inspection lead to sign the release record before testing, then attach the result when it becomes available.
  • ☐ C. Use the supplier's existing confidence statement as the required result without completing the planned inspection.
  • ☐ D. Complete the required inspection and document its result before releasing the batch.
Show answer and explanation

Response: D

Final answer: Complete the required inspection and document its result before releasing the batch.

The inspection is a prerequisite. Complete and document it to obtain the evidence required by the plan before recommending release of this batch, since no approved exception applies.

Question 141

After sending a progress report, an associate discovers that one completed-work figure counted the same inspection twice. The error materially overstates progress. The sponsor will use the report tomorrow to decide whether to release the next funding installment. What should the associate do first?

  • ☐ A. Ask the inspector to repeat the inspection before notifying the sponsor of the reporting error.
  • ☐ B. Wait for the routine reporting cycle and use the corrected figure in the next report.
  • ☐ C. Notify the appropriate authority promptly and provide a corrected figure and explanation of its effect.
  • ☐ D. Correct the internal workbook now but leave the distributed report until the funding decision is complete.
Show answer and explanation

Response: C

Final answer: Notify the appropriate authority promptly and provide a corrected figure and explanation of its effect.

Tomorrow's funding decision could rely on the duplicate count. Correct the distributed figure promptly. Notify the appropriate authority and explain how the overstatement changes the progress account before the sponsor uses it.

Question 142

A solution conforms to every recorded screen requirement, but user trials show that the intended reduction in claim-handling effort has not occurred. Which question should the analyst investigate?

  • ☐ A. Whether the passed screen tests alone establish the operating benefit despite the user-trial result.
  • ☐ B. Whether the business need should be revised to match the delivered screens before investigating the trial evidence.
  • ☐ C. Whether the delivered solution and requirements adequately address the agreed business need.
  • ☐ D. Whether the user-trial result can be excluded because it measures an outcome outside screen conformance.
Show answer and explanation

Response: C

Final answer: Whether the delivered solution and requirements adequately address the agreed business need.

User effort has not fallen. Investigate whether the requirements and delivered solution adequately address that business need, using the trials to examine the intended outcome. The passing screen checks establish verification of the specified behavior.

Question 143

A meeting cannot resolve a design choice because a required load calculation is missing. What should the facilitator record for effective follow-up?

  • ☐ A. Schedule another general discussion without assigning responsibility for the missing calculation.
  • ☐ B. Record the design choice as provisionally approved and let the implementation team obtain the calculation afterward.
  • ☐ C. Record that all options remain acceptable and let each specialist select one independently.
  • ☐ D. An assigned owner and due date for obtaining the calculation needed for the decision.
Show answer and explanation

Response: D

Final answer: An assigned owner and due date for obtaining the calculation needed for the decision.

The design decision needs a load calculation that has not been supplied. Assign responsibility for obtaining that evidence and agree on a due date, giving the missing information an accountable follow-up action.

Question 144

The chart shows actual remaining work and an ideal reference line over five working days. Select the labeled region containing the actual remaining-work point on day 4. The reference line is a planning comparison, not a guarantee of completion.

DayWorkremaining012345010203040Solid: actualDashed: idealABCD

Scroll the diagram sideways on a narrow screen.

Diagram text description

Remaining-work chart. Solid actual line: day 0: 40 units, day 1: 34 units, day 2: 30 units, day 3: 24 units, day 4: 18 units, day 5: 9 units. Dashed ideal line: day 0: 40 units, day 1: 32 units, day 2: 24 units, day 3: 16 units, day 4: 8 units, day 5: 0 units. Labeled regions: A: day 2, 30 units, B: day 4, 8 units, C: day 4, 18 units, D: day 5, 9 units.

Record the label of the selected region.

Show answer and explanation

Response: C

Final answer: Region C

Label C marks 18 remaining units. On day 4, that point lies on the solid line for actual work remaining, supplying the observation requested from the chart.

Question 145

A team scores two options from 1 to 5, with higher scores better. Cost has weight 0.6 and reliability 0.4. Option A scores 5 for cost and 2 for reliability. Option B scores 3 for cost and 4 for reliability. Which has the higher weighted score?

  • ☐ A. Option B: 3.8 compared with Option A: 3.4.
  • ☐ B. Both options: 3.5 because each has a raw total of 7.
  • ☐ C. Option A: 3.8 compared with Option B: 3.4.
  • ☐ D. Option B: 3.6 compared with Option A: 3.2.
Show answer and explanation

Response: C

Final answer: Option A: 3.8 compared with Option B: 3.4.

Multiply each score by its weight. For Option A, 5 times 0.6 plus 2 times 0.4 totals 3.8. Apply the same weights to B's scores of 3 and 4 to obtain 3.4, leaving A selected by the stated matrix rule.

Question 146

A backlog item states: A user can reserve an available seat and receives confirmation; if no seats remain, the request is rejected without charging the user. Which evidence best demonstrates the stated behavior?

  • ☐ A. A test confirms an available reservation but records a charge for the rejected full-capacity request.
  • ☐ B. Tests show confirmation for an available seat and rejection without a charge when no seats remain.
  • ☐ C. A screenshot shows a reservation button and confirmation text without exercising either availability case.
  • ☐ D. A performance test shows fast reservation responses without checking confirmation or rejected-request charging.
Show answer and explanation

Response: B

Final answer: Tests show confirmation for an available seat and rejection without a charge when no seats remain.

Test both availability cases. Reservation confirmation verifies the available-seat outcome, and the full-capacity case requires checking the rejection result and the billing record to establish that the rejected request leaves the user uncharged.

Question 147

An associate is upset by an unexpected change request. They know an immediate angry reply would derail the review. Which response most directly demonstrates self-management?

  • ☐ A. Suppress discussion of the project concern entirely rather than return to its factual implications.
  • ☐ B. Ask the requester to take responsibility for preventing the associate's emotional reaction.
  • ☐ C. Identify that the request triggers anger, then send the original angry reply without regulating it.
  • ☐ D. Pause, regulate the reaction and return to a factual discussion of the request.
Show answer and explanation

Response: D

Final answer: Pause, regulate the reaction and return to a factual discussion of the request.

The associate recognizes the anger. Pausing to regulate that response before returning to a factual discussion of the request demonstrates self-management and keeps the review workable.

Question 148

An analyst needs detailed accounts of how four specialist users handle unusual cases. Each user has different expertise, and follow-up questions are expected. Which method best fits?

  • ☐ A. A general workshop that focuses on the most common case and gives no time for each specialist's exceptions.
  • ☐ B. A fixed-choice survey designed to produce comparable counts but offering no follow-up exploration.
  • ☐ C. Individual stakeholder interviews
  • ☐ D. A review of historical reports used in place of asking how these specialists handle their unusual cases.
Show answer and explanation

Response: C

Final answer: Individual stakeholder interviews

Separate interviews let the analyst ask follow-up questions suited to each specialist's experience of unusual cases, obtaining the detailed exception and requirements accounts this work needs.

Question 149

A proposed project has a business justification but has not been formally authorized. Which artifact provides formal authorization and establishes the manager's authority to apply organizational resources as specified?

  • ☐ A. The business case explaining why the investment should be undertaken.
  • ☐ B. The project management plan describing how work will be executed and controlled.
  • ☐ C. The project charter
  • ☐ D. The product roadmap communicating intended capabilities across future releases.
Show answer and explanation

Response: C

Final answer: The project charter

The charter formally establishes the project and the manager's specified authority to apply organizational resources, supplying the authorization still missing after the proposed work received a business justification.

Question 150

An adaptive team meets two iterations by working every weekend. Management proposes making that schedule permanent. Which response best follows the sustainable-development principle?

  • ☐ A. Adjust the workload and way of working so delivery can continue at a maintainable pace.
  • ☐ B. Reduce testing time while keeping the same workload and deadlines.
  • ☐ C. Keep weekend work as the permanent baseline because two iterations succeeded.
  • ☐ D. Set a higher forecast to make the team sustain the same overtime.
Show answer and explanation

Response: A

Final answer: Adjust the workload and way of working so delivery can continue at a maintainable pace.

Assess maintainable capacity before setting a permanent delivery schedule. Weekend work supplied the effort for these two iterations, so the workload and working practices need evaluation for continuing delivery under the sustainable-development principle, with required completion standards preserved.